Which type of risk diagram is useful for showing time ordering of events?
Answer(s): C
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
Answer(s): D
A required input for Create WBS is a project:
5.3.3.1 Project Scope StatementThe project scope statement is the description of the project scope, major deliverables, assumptions, and constraints. The project scope statement documents the entire scope, including project and product scope. It describes, in detail, the project’s deliverables and the work required to create those deliverables. It also provides a common understanding of the project scope among project stakeholders. It may contain explicit scope exclusions that can assist in managing stakeholder expectations. It enables the project team to perform more detailed planning, guides the project team’s work during execution, and provides the baseline for evaluating whether requests for changes or additional work are contained within or outside the project’s boundaries.The degree and level of detail to which the project scope statement defines the work that will be performed and the work that is excluded can help determine how well the project management team can control the overall project scope. The detailed project scope statement, either directly, or by reference to other documents, includes the following:Product scope description. Progressively elaborates the characteristics of the product, service, or result described in the project charter and requirements documentation.Acceptance criteria. A set of conditions that is required to be met before deliverables are accepted.Deliverable. Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project. Deliverables also include ancillary results, such as project management reports and documentation. These deliverables may be described at a summary level or in great detail. Project exclusion. Generally identifies what is excluded from the project. Explicitly stating what is out of scope for the project helps to manage stakeholders’ expectations.Constraints. A limiting factor that affects the execution of a project or process. Constraints identified with the project scope statement list and describe the specific internal or external restrictions or limitations associated with the project scope that affect the execution of the project, for example, a predefined budget or any imposed dates or schedule milestones that are issued by the customer or performing organization. When a project is performed under an agreement, contractual provisions will generally be constraints. Information on constraints may be listed in the project scope statement or in a separate log.Assumptions. A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration. Also describes the potential impact of those factors if they prove to be false. Project teams frequently identify, document, and validate assumptions as part of their planning process. Information on assumptions may be listed in the project scope statement or in a separate log.The project team must complete a scope statement for developing a common understanding of the project scope among stakeholders. This lists project deliverables - summary level sub-products, whose full and satisfactory delivery marks the completion of the project.Process: 5.4 Create WBSDefinition: WBS is the process of subdividing project deliverables and project work into smaller, more manageable components.Key Benefit: The key benefit of this process is that it provides a structured vision of what has to be delivered.Inputs1. Scope management plan2. Project scope statement3. Requirements documentation4. Enterprise environmental factors5. Organizational process assetsTools & Techniques1. Decomposition2. Expert judgmentOutputs1. Scope baseline2. Project documents updates
Which of the following statements is true regarding project and product lifecycles?
Answer(s): A
Which tool or technique is used in Close Procurements?
12.4.2.1 Procurement AuditsA procurement audit is a structured review of the procurement process originating from the Plan Procurement Management process through Control Procurements. The objective of a procurement audit is to identify successes and failures that warrant recognition in the preparation or administration of other procurement contracts on the project, or on other projects within the performing organization.12.4 Close ProcurementsThe process of completing each project procurement.Key Benefit: The key benefit of this process is that it documents agreements and related documentation for future reference.Inputs1. Project management plan2. Procurement documentsTools & Techniques1. Procurement audits2. Procurement negotiations3. Records management systemOutputs1. Closed procurements2. Organizational process assets updates