Free CAPM Exam Braindumps
Certified Associate in Project Management (PMI-100) Questions 576–580 (page: 117)

Updated On: 9-Feb-2026

Which of the following is an output of Direct and Manage Project Execution?

  1. Project management plan
  2. Change request status updates
  3. Organizational process assets updates
  4. Work performance information

Answer(s): D



Which of the following is an input to Develop Human Resource Plan?

  1. Team performance assessment
  2. Roles and responsibilities
  3. Staffing management plan
  4. Enterprise environmental factors

Answer(s): D



Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

  1. Performance organizations
  2. Schedule baselines
  3. Work performance measurements
  4. Change requests

Answer(s): C



Testing falls into which of the following categories of cost of quality?

  1. Internal failure costs
  2. Prevention costs
  3. Appraisal costs
  4. External failure costs

Answer(s): C

Explanation:

Cost of Quality. (COQ) A method of determining the costs incurred to ensure quality. Prevention and appraisal costs (cost of conformance) include costs for quality planning, quality control (QC), and quality assurance to ensure compliance to requirements (i.e., training, QC systems, etc.). Failure costs (cost of nonconformance) include costs to rework products, components, or processes that are non-compliant, costs of warranty work and waste, and loss of reputation.



Another name for an Ishikawa diagram is:

  1. cause and effect diagram.
  2. control chart.
  3. flowchart.
  4. histogram.

Answer(s): A