What does a CPI value greater than 1.0 indicate?

  1. Cost right at the estimated value
  2. Cost under the estimated value
  3. Cost right at the actual value
  4. Cost over the estimated value

Answer(s): B

Explanation:

CPI = EV / AC



Which of the following is an output from Control Scope?

  1. Change requests
  2. Variance analysis
  3. Accepted deliverables
  4. Requirements documentation

Answer(s): A

Explanation:

Process: 5.6 Control Scope
Definition: The process of monitoring the status of the project and product scope and managing changes to the scope baseline.
Key Benefit: The key benefit of this process is that it allows the scope baseline to be maintained throughout the project.

Inputs
Project management plan Requirements documentation Requirements traceability matrix Work performance data Organizational process assets

Tools & Techniques
Variance analysis
Outputs
Work performance information
Change requests
Project management plan updates Project documents updates Organizational process assets updates



Managing procurement relationships and monitoring contract performance are part of which process?

  1. Conduct Procurements
  2. Plan Procurements
  3. Administer Procurements
  4. Close Procurements

Answer(s): C



Which technique is commonly used for the Perform Quantitative Risk Analysis process?

  1. Brainstorming
  2. Strategies for opportunities
  3. Decision tree analysis
  4. Risk data quality assessment

Answer(s): C

Explanation:

Decision Tree Analysis. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

- Can only be used with discrete data.

Process: 11.4 Perform Quantitative Risk Analysis
Definition: The process of numerically analyzing the effect of identified risks on overall project objectives.
Key Benefit: The key benefit of this process is that it produces quantitative risk information to support decision making in order to reduce project uncertainty.

Inputs
Risk management plan Cost management plan Schedule management plan Risk register
Enterprise environmental factors Organizational process assets

Tools & Techniques

Data gathering and representation techniques Quantitative risk analysis and modeling techniques Expert judgment

Outputs
1. Project documents updates



In which type of organizational structure are staff members grouped by specialty?

  1. Functional
  2. Projectized
  3. Matrix
  4. Balanced

Answer(s): A