Free CAPM Exam Braindumps
Certified Associate in Project Management (PMI-100) Questions 351–355 (page: 72)

Updated On: 9-Feb-2026

Which of the following is contained within the communications management plan?

  1. An organizational chart
  2. Glossary of common terminology
  3. Organizational process assets
  4. Enterprise environmental factors

Answer(s): B

Explanation:

10.1.3.1 Communications Management Plan
The communications management plan is a component of the project management plan that describes how project communications will be planned, structured, monitored, and controlled. The plan contains the following information:
Stakeholder communication requirements;
Information to be communicated, including language, format, content, and level of detail; Reason for the distribution of that information;
Time frame and frequency for the distribution of required information and receipt of acknowledgment or response, if applicable;
Person responsible for communicating the information;
Person responsible for authorizing release of confidential information; Person or groups who will receive the information;
Methods or technologies used to convey the information, such as memos, e-mail, and/or press releases; Resources allocated for communication activities, including time and budget;
Escalation process identifying time frames and the management chain (names) for escalation of issues that cannot be resolved at a lower staff level;
Method for updating and refining the communications management plan as the project progresses and develops;
Glossary of common terminology;
Flow charts of the information flow in the project, workflows with possible sequence of authorization, list of reports, and meeting plans, etc.; and
Communication constraints usually derived from a specific legislation or regulation, technology, and organizational policies, etc.

The communications management plan can also include guidelines and templates for project status meetings, project team meetings, e-meetings, and e-mail messages. The use of a project website and project management software can also be included if these are to be used in the project.



Which of the following is a tool and technique for Estimate Activity Durations?

  1. Parametric estimating
  2. Monte Carlo analysis
  3. Alternatives analysis
  4. Bottom-up estimating

Answer(s): A

Explanation:

7.2.2.3 Parametric Estimating
Parametric estimating uses a statistical relationship between relevant historical data and other variables (e.g., square footage in construction) to calculate a cost estimate for project work. This technique can produce higher levels of accuracy depending upon the sophistication and underlying data built into the model. Parametric cost estimates can be applied to a total project or to segments of a project, in conjunction with other estimating methods.

Process: 6.5 Estimate Activity Durations
Definition: The process of estimating the number of work periods needed to complete individual activities with estimated resources.
Key Benefit: The key benefit of this process is that it provides the amount of time each activity will take to complete, which is a major input into the Develop Schedule process.

Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Activity resource requirements
5. Resource calendars
6. Project scope statement
7. Risk register
8. Resource breakdown structure
9. Enterprise environmental factors
10. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Three-point estimating
5. Group decision-making techniques
6. Reserve analysis

Outputs
1. Activity duration estimates
2. Project documents updates



Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

  1. Complete project phase
  2. Project life
  3. The project life cycle
  4. Project cycle

Answer(s): C



Which schedule network analysis technique modifies the project schedule to account for limited resources?

  1. Human resource planning
  2. Fast tracking
  3. Critical chain method
  4. Rolling wave planning

Answer(s): C

Explanation:

6.6.2.3 Critical Chain Method
The critical chain method (CCM) is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties. It is developed from the critical path method approach and considers the effects of resource allocation, resource optimization, resource leveling, and activity duration uncertainty on the critical path determined using the critical path method. To do so, the critical chain method introduces the concept of buffers and buffer management. The critical chain method uses activities with durations that do not include safety margins, logical relationships, and resource availability with statistically determined buffers composed of the aggregated safety margins of activities at specified points on the project schedule path to account for limited resources and project uncertainties. The resource-constrained critical path is known as the critical chain.



Which of the following is an output of the Monitor and Control Project Work process?

  1. Change requests
  2. Performance reports
  3. Organizational process assets
  4. Project management plan

Answer(s): A

Explanation:

Process: 4.4. Monitor and Control Project Work
Definition: Monitor and Control Project Work is the process of tracking, reviewing, and reporting the progress to meet the performance objectives defined in the project management plan.
Key Benefit: The key benefit of this process is that it allows stakeholders to understand the current state of the project, the steps taken, and budget, schedule, and scope forecasts.

Inputs
1. Project management plan
2. Schedule forecasts
3. Cost forecasts
4. Validated changes
5. Work performance information
6. Enterprise environmental factors
7. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Project management information system
4. Meetings

Outputs
1. Change requests
2. Work performance reports
3. Project management plan updates
4. Project documents updates



Viewing page 72 of 222
Viewing questions 356 - 360 out of 1320 questions


Post your Comments and Discuss PMI CAPM exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!