Certified Associate in Project Management (PMI-100) Questions 356–360 (page: 73)

Updated On: 9-Feb-2026

Which of the following statements correctly characterizes pull communication?

  1. It includes letters, memos, reports, emails, and faxes.
  2. It requires recipients to access communication content at their own discretion.
  3. It is the most efficient way to ensure a common understanding among all participants.
  4. It is primarily used when the volume of information to be transferred is minimal.

Answer(s): B



When would resource leveling be applied to a schedule model?

  1. Before constraints have been identified
  2. Before it has been analyzed by the critical path method
  3. After it has been analyzed by the critical path method
  4. After critical activities have been removed from the critical path

Answer(s): C

Explanation:

6.6.2.2 Critical Path Method
The critical path method, which is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. This schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard for any resource limitations by performing a forward and backward pass analysis through the schedule network, as shown in Figure 6-18. In this example the longest path includes activities A, C, and D, and, therefore, the sequence of A-C-D is the critical path. The critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration. The resulting early and late start and finish dates are not necessarily the project schedule, rather they indicate the time periods within which the activity could be executed, using the parameters entered in the schedule model for activity durations, logical relationships, leads, lags, and other known constraints. The critical path method is used to calculate the amount of scheduling flexibility on the logical network paths within the schedule model.

On any network path, the schedule flexibility is measured by the amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint, and is termed “total float.” A CPM critical path is normally characterized by zero total float on the critical path. As implemented with PDM sequencing, critical paths may have positive, zero, or negative total float depending on constraints applied. Any activity on the critical path is called a critical path activity. Positive total float is caused when the backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during forward pass calculation. Negative total float is caused when a constraint on the late dates is violated by duration and logic. Schedule networks may have multiple near-critical paths. Many software packages allow the user to define the parameters used to determine the critical path(s). Adjustments to activity durations (if more resources or less scope can be arranged), logical relationships (if the relationships were discretionary to begin with), leads and lags, or other schedule constraints may be necessary to produce network paths with a zero or positive total float. Once the total float for a network path has been calculated, then the free float—the amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint—can also be determined. For example the free float for Activity B, in Figure 6-18, is 5 days.



Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

  1. Project Integration Management
  2. Project Communications Management
  3. Project Information Management System (PIMS)
  4. Project Scope Management

Answer(s): B



Which of the following tools or techniques is used for Estimate Activity Durations?

  1. Critical path method
  2. Rolling wave planning
  3. Precedence diagramming method
  4. Parametric estimating

Answer(s): D

Explanation:

7.2.2.3 Parametric Estimating
Parametric estimating uses a statistical relationship between relevant historical data and other variables (e.g., square footage in construction) to calculate a cost estimate for project work. This technique can produce higher levels of accuracy depending upon the sophistication and underlying data built into the model. Parametric cost estimates can be applied to a total project or to segments of a project, in conjunction with other estimating methods.

Process: 6.5 Estimate Activity Durations
Definition: The process of estimating the number of work periods needed to complete individual activities with estimated resources.
Key Benefit: The key benefit of this process is that it provides the amount of time each activity will take to complete, which is a major input into the Develop Schedule process.

Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Activity resource requirements
5. Resource calendars
6. Project scope statement
7. Risk register
8. Resource breakdown structure
9. Enterprise environmental factors
10. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Three-point estimating
5. Group decision-making techniques
6. Reserve analysis

Outputs
1. Activity duration estimates
2. Project documents updates



Information collected on the status of project activities being performed to accomplish the project work is known as what?

  1. Project management information system
  2. Work performance information
  3. Work breakdown structure
  4. Variance analysis

Answer(s): B

Explanation:

4.4.1.5 Work Performance Information
Work performance information is the performance data collected from various controlling processes, analyzed in context, and integrated based on relationships across areas. Thus work performance data has been transformed into work performance information. Data in itself cannot be used in the decision-making process as it has only out-of-context meaning. Work performance information, however, is correlated and contextualized, and provides a sound foundation for project decisions.
Work performance information is circulated through communication processes. Examples of performance information are status of deliverables, implementation status for change requests, and forecasted estimates to complete.



Viewing page 73 of 222
Viewing questions 361 - 365 out of 1320 questions