Which tool is used to develop technical details within the project management plan?
Answer(s): A
4.1.2.1 Expert JudgmentExpert judgment is often used to assess the inputs used to develop the project charter. Expert judgment is applied to all technical and management details during this process. Such expertise is provided by any group or individual with specialized knowledge or training and is available from many sources, including:Other units within the organization, Consultants,Stakeholders, including customers or sponsors, Professional and technical associations, Industry groups,Subject matter experts (SME), and Project management office (PMO).
What is the name of a graphic display of project team members and their reporting relationships?
Answer(s): C
Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?
Answer(s): D
5.4.3.1 Scope BaselineThe scope baseline is the approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison. It is a component of the project management plan. Components of the scope baseline include:Project scope statement. The project scope statement includes the description of the project scope, major deliverables, assumptions, and constraints.WBS. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Each descending level of the WBS represents an increasingly detailed definition of the project work. The WBS is finalized by assigning each work package to a control account and establishing a unique identifier for that work package from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information. A control account is a management control point where scope, budget, actual cost, and schedule are integrated and compared to the earned value for performance measurement. Control accounts are placed at selected management points in the WBS. Each control account may include one or more work packages, but each of the work packages should be associated with only one control account. A control account may include one or more planning packages. A planning package is a work breakdown structure component below the control account with known work content but without detailed schedule activities.WBS dictionary. The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. The WBS dictionary is a document that supports the WBS. Information in the WBS dictionary may include, but is not limited to:○ Code of account identifier,○ Description of work,○ Assumptions and constraints,○ Responsible organization,○ Schedule milestones, ○ Associated schedule activities,○ Resources required,○ Cost estimates,○ Quality requirements,○ Acceptance criteria,○ Technical references, and○ Agreement information
What type of reward can hurt team cohesiveness?
Answer(s): B
Recognition and rewards. Clear criteria for rewards and a planned system for their use help promote and reinforce desired behaviors. To be effective, recognition and rewards should be based on activities and performance under a person’s control. For example, a team member who is to be rewarded for meeting cost objectives should have an appropriate level of control over decisions that affect expenses. Creating a plan with established times for distribution of rewards ensures that recognition takes place and is not forgotten.Recognition and rewards are part of the Develop Project Team process (Section 9.3).Process: 9.3 Develop Project TeamDefinition: The process of improving competencies, team member interaction, and overall team environment to enhance project performance.Key Benefit: The key benefit of this process is that it results in improved teamwork, enhanced people skills and competencies, motivated employees, reduced staff turnover rates, and improved overall project performance.Inputs1. Human resource management plan2. Project staff assignments3. Resource calendarsTools & Techniques1. Interpersonal skills2. Training3. Team-building activities4. Ground rules5. Colocation6. Recognition and rewards7. Personnel assessment toolsOutputs1. Team performance assessments2. Enterprise environmental factors updates
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
6.2.2.2 Rolling Wave PlanningRolling wave planning is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level. It is a form of progressive elaboration.Therefore, work can exist at various levels of detail depending on where it is in the project life cycle. During early strategic planning, when information is less defined, work packages may be decomposed to the known level of detail. As more is known about the upcoming events in the near term, work packages can be decomposed into activities.