A knowledge area defines a subset of program management and its processes within that domain. For example, the knowledge area of quality management includes the processes related directly to quality management only. Which knowledge area ensures that all knowledge areas interact correctly with one another?

  1. Program benefits management
  2. Program management planning
  3. Integration management
  4. Communications management

Answer(s): C



You are the program manager of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

  1. Project charter for each project
  2. Program human resource management plan
  3. Project scope statement
  4. Program management charter

Answer(s): A



You are the program manager for your company and evaluating the sellers to determine the seller to buy from. In your analysis you've created a histogram to display the pros and cons for each seller. You've created five categories of interest and assigned values to each category for each vendor. Your five categories are:

-Cost
-Schedule
-Experience
-Certification
-Warranty

Each category has a different point value and the vendor that receives the maximum points in total will win the contract. What type of seller evaluation are you performing?

  1. Monte Carlo simulation
  2. Expert judgment
  3. Weighted scoring model
  4. Benchmarking

Answer(s): C



Kelly's program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They've asked Kelly to use a schedule duration compression technique that will help the program finish on time. The technique that Kelly can use, however, should not add costs to the program. What duration compression technique should Kelly use in this instance?

  1. Crash the program
  2. Add lead time to the program
  3. Trim the program scope
  4. Fast track the program

Answer(s): D