A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?

  1. Defect repair validation
  2. Lesson learned documentation
  3. Corrective actions
  4. Preventive actions

Answer(s): A



Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

  1. Resource breakdown structure
  2. Resource management chart
  3. Stakeholder analysis chart
  4. RACI chart

Answer(s): C



Which one of the following is the best example of transference?

  1. Your program has some very dangerous activities so you hire a training company to train your program team.
  2. Your program creates an opportunity that your company can realize on its own so it brings in a competitor to help seize the opportunity.
  3. Your program must be completed by a given deadline as government inspectors are scheduled to review the work to determine its accuracy.
  4. Your program is dealing with a new technology that you and your program team are not familiar with so you hire a consulting company to complete this work for you.

Answer(s): D



You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule.
Based on this information, what is the schedule performance index (SPI) for this program?

  1. $821,065
  2. .86
  3. 1.05
  4. .89

Answer(s): B