You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?

  1. Program requirements for resource competency levels
  2. Structure of the program management team
  3. Metrics and qualifications for program acceptance
  4. Location of the program work

Answer(s): B



You are the program manager for your organization. A new program is about to initiated and Marcy, your assistant, asks you about the themes that all new programs must map to. All of the following are themes that you can discuss with Marcy except for which one is not a program theme?

  1. Stakeholder management
  2. Requirements analysis
  3. Benefits management
  4. Program governance

Answer(s): B



Part of program management is to understand how the communication model works in a program. The program manager must be able to effectively communicate with the program team and stakeholders. What component of the communication model is responsible for carrying the message?

  1. Medium
  2. Sender
  3. Decoder
  4. Encoder

Answer(s): A



You are the program manager for your organization and are planning the composition of the project team. In your organization resources are used from throughout the company and may serve on more than one project. While you, the program manager, will have most of the authority on the program you want the project managers to have authority over the project decisions. What type of an organizational structure does your organization have?

  1. Strong Matrix
  2. Functional
  3. Weak Matrix
  4. Projectized

Answer(s): A