At what point in the project is the risk of failing to achieve the project objectives the greatest?

  1. During project planning
  2. During the project execution
  3. At the project start
  4. At the end of the project

Answer(s): C



Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of the following is the best chart for Gina in this situation?

  1. Cause and effect chart
  2. Pareto chart
  3. Control chart
  4. Ishikawa chart

Answer(s): B



You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only work 20 hours per week on the program. What is this limit of resource hours in a time period known as?

  1. Resource leveling heuristic
  2. Resource requirements
  3. Program risk
  4. Resource utilization

Answer(s): A



You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?

  1. Final program audit report
  2. Audit of program financials
  3. Lessons learned documentation
  4. Certificate of program completion

Answer(s): D



You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of the following?

  1. How quality control will be included in the scope
  2. How changes may be allowed to enter the program scope
  3. How the program scope will be created for your program
  4. How the program scope will be controlled

Answer(s): A