Free PGMP Exam Braindumps (page: 36)

Page 35 of 113

In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?

  1. Program governance
  2. Organizational process assets
  3. Program standards
  4. Process analysis

Answer(s): A



Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete at this, but due to some vendor delays your program is running just a bit late. Management is concerned that your program will not be able to recoup the costs of the expenses.

They've asked you to determine the cost variance for the program. What is the cost variance based on this information?

  1. -$27,500
  2. -$77,500
  3. -$61,111
  4. .90

Answer(s): A



You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project's network diagram. Which one of the following is the best definition of the critical path?

  1. It is the path that carries the most risk of project failure.
  2. It is the path that reveals the earliest date the project can finish.
  3. It is the path with the most important activities in the project.
  4. It is the duration of all the project activities if the labor is summed.

Answer(s): B



You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?

  1. It is the review of the impact of the change on the program's knowledge areas.
  2. It is the review of the impact of the change on the time, cost, scope, and quality baselines.
  3. It is the review of the impact of the change on the program's triple constraints.
  4. It is the review of the impact of the change on the program's Iron Triangle.

Answer(s): A