Paul is the program manager for his company. He along with his team is working on the Monitor and Control Program Changes process. The process will need several inputs. Which one of the following items is NOT an input to the Monitor and Control Program Changes process in the program management?

  1. Change request log
  2. Approved change requests
  3. Change requests
  4. Program management plan

Answer(s): B



Which of the following statements are true regarding program scope changes? (Choose three.)

  1. Scope changes may originate from the stake holders.
  2. Change requests for a particular project have to be approved by the project manager irrespective of their potential impact on multiple projects.
  3. The program has a change control board that analyzes changes at the program level.
  4. The change control process on a program is often hierarchical.

Answer(s): A,C,D



You are the program manager for your organization. Your current program has fourteen projects and one project manager in your program is about to close her project. She will need all of the following inputs to the close project process except for which one?

  1. Project management plan
  2. Organizational process assets
  3. Project deliverables
  4. Quality control measurements

Answer(s): D



What is another term that can be assigned to the pre-program analysis and research to determine if a program should be initiated?

  1. Program scope statement definition
  2. Feasibility study creation
  3. Business case creation
  4. Program charter creation

Answer(s): B



You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this scenario?

  1. Statement of work
  2. Request for quote
  3. Proposal
  4. Program charter

Answer(s): B