Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?

  1. Project managers
  2. Hans
  3. Program director
  4. Hans and each project manager

Answer(s): A



What is the primary purpose of a project kick-off meeting?

  1. To establish why the project has been initiated.
  2. To establish the direction and purpose of the project management plan.
  3. To establish the roles and responsibilities of the stakeholders.
  4. To establish who the project manager and project sponsor are for the project.

Answer(s): A



At what point in the project is the risk of failing to achieve the project objectives the greatest?

  1. During project planning
  2. During the project execution
  3. At the project start
  4. At the end of the project

Answer(s): C



Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of the following is the best chart for Gina in this situation?

  1. Cause and effect chart
  2. Pareto chart
  3. Control chart
  4. Ishikawa chart

Answer(s): B