PGMP Practice Test & Exam Dumps
Program Management Professional Questions 231–235 (page: 48)

Updated On: 10-Feb-2026

A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?

  1. .93
  2. .82
  3. $323,889
  4. -$38,889

Answer(s): A



What document should you provide to the vendors if you're only interested for a set fee for their materials?

  1. IFB
  2. RFP
  3. RFI
  4. SOW

Answer(s): A



Which earned value management formula can help you determine how likely it is that you'll complete the program based on the amount of cash left in the program budget?

  1. Estimate at completion
  2. Variance at completion
  3. To-complete performance index
  4. Estimate to complete

Answer(s): C



You are the program manager for your organization and you are dealing with your program stakeholders. You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play. The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule beyond a given due date for the program. They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion. What type of risk response are your program stakeholders recommending in this situation?

  1. Avoidance
  2. Mitigation
  3. Transference
  4. Workaround

Answer(s): B



Communication is large percentage of program execution as the program manager must communicate with
the appropriate stakeholders. In larger programs face-to-face communication is not always possible. When emails are used what verbal aspect of communication is lost?

  1. Barriers
  2. Noise
  3. Nonverbal
  4. Paralingual

Answer(s): D