PGMP Practice Test & Exam Dumps
Program Management Professional Questions 306–310 (page: 63)

Updated On: 10-Feb-2026

A component project of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations.
What should the program manager do next?

  1. Reassign the component project manager to another component project or activity
  2. Verify that the benefits were delivered and authorize component project closure
  3. Conduct a program audit to confirm that the component project is complete
  4. Keep the component project open until the program benefits are realized

Answer(s): B



An organization is embarking on a new program aligned with its strategic objectives. The new program has a high level of risk due to the rapidly changing technical landscape in which the organization operates. The organization has mature program management capabilities, as measured by its resources, intellectual assets, and management processes.
Given the organization’s history of delivering successful programs, what should the program manager do as part of the planning process?

  1. Interview the program managers and stakeholders of previous programs to learn from their experiences.
  2. Review the organization’s strategic objectives, risk tolerance, and compliance processes, which may provide knowledge about past programs.
  3. Consult the repository developed as part of the organization’s knowledge management initiative to capture best practices and lessons learned.
  4. Hire independent industry specialists and subject matter experts (SMEs) to provide additional information about market trends and uncertainties in the external environment.

Answer(s): C



The program manager wants to increase the team’s commitment to the program objectives. The program manager should do which of the following?

  1. Work with the sponsor to identify the organization’s best practices.
  2. Work with the program stakeholders and program management office to identify the organization’s best practices.
  3. Work with the program management office to identify the organization’s best practices.
  4. Work with the sponsor, program stakeholders, and the program management office to identify the organization’s best practices.

Answer(s): D



A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision:


Which project should the program manager select to be cancelled?

  1. Project A
  2. Project B
  3. Project C
  4. Project D

Answer(s): D



In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS).
During the meeting, the master scheduler indicates that the master program schedule should include which of the following?

  1. Program benefits and all component project activities
  2. Component resources and their activity assignment/responsibility metrics
  3. Program-level activities and integrated component projects
  4. Program activities, component activities, and all other work

Answer(s): D



Viewing page 63 of 126
Viewing questions 311 - 315 out of 713 questions