A component project of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations.What should the program manager do next?
Answer(s): B
An organization is embarking on a new program aligned with its strategic objectives. The new program has a high level of risk due to the rapidly changing technical landscape in which the organization operates. The organization has mature program management capabilities, as measured by its resources, intellectual assets, and management processes.Given the organization’s history of delivering successful programs, what should the program manager do as part of the planning process?
Answer(s): C
The program manager wants to increase the team’s commitment to the program objectives. The program manager should do which of the following?
Answer(s): D
A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision:Which project should the program manager select to be cancelled?
In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS).During the meeting, the master scheduler indicates that the master program schedule should include which of the following?