Program Management Professional Questions 311–315 (page: 64)

Updated On: 10-Feb-2026

A program manager has a multiple-project program that is scheduled to be completed by year’s end. During the program delivery phases of the projects, several mandatory changes are identified that would extend the program’s completion date.
What is the next step for the program manager?

  1. Apply resource leveling to ensure the program is completed on schedule
  2. Update the schedule to reflect the extended completion date
  3. Adjust working hours to ensure the program is completed on schedule
  4. Submit a change request to extend the program schedule

Answer(s): D



During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.
What should the program manager do?

  1. Communicate to the program sponsor regarding the additional estimated cost and request a change order.
  2. Determine which component projects have excess capacity and rebalance those resources to the project that needs additional hours.
  3. Request that the project manager make the team members work additional hours and not bill the project.
  4. Talk with the project manager and find ways to reduce hours in another part of the project.

Answer(s): B



An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.
What should the program manager do next?

  1. Assign resources to the schedule and report the revised delivery date to the project managers.
  2. Work with the project managers to refine the project schedules and deliverables to align with the program milestones.
  3. Revise the project schedules to meet the program schedule and communicate to stakeholders.
  4. Integrate the project schedules into the program schedule and report the revised delivery date to the project managers.

Answer(s): B



The program director of a four-year program, estimated to require 600,000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the test phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation.
Which of the following metrics should the PMO capture on a monthly basis?

  1. Billable hours charged to the program, non-billable hours charged to the program, quantity of defects per full-time equivalent (FTE)
  2. Absenteeism rate, staff turnover, quantity of defects, and total hours worked on the program
  3. Amount of hours spent on rework of software coding, retesting, and on non-rework activities
  4. Absenteeism rate, staff turnover, leave liability, and quantity of defects per full-time equivalent

Answer(s): B



Stakeholders ask the program manager to assess reasons for the project’s delay and provide a report. Also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget.
The program manager distributes information in accordance with which of the following?

  1. Stakeholder engagement plan
  2. Program governance charter
  3. Schedule management plan
  4. Communications management plan

Answer(s): C



Viewing page 64 of 126
Viewing questions 316 - 320 out of 713 questions