A program manager has a multiple-project program that is scheduled to be completed by year’s end. During the program delivery phases of the projects, several mandatory changes are identified that would extend the program’s completion date.What is the next step for the program manager?
Answer(s): D
During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.What should the program manager do?
Answer(s): B
An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.What should the program manager do next?
The program director of a four-year program, estimated to require 600,000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the test phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation.Which of the following metrics should the PMO capture on a monthly basis?
Stakeholders ask the program manager to assess reasons for the project’s delay and provide a report. Also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget.The program manager distributes information in accordance with which of the following?
Answer(s): C