Free PMI-ACP Exam Braindumps (page: 10)

Page 10 of 81

Two similar stories, A and B, are estimated at 3 story points. Story C, estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.
What should the agile practitioner do?

  1. Assign story B more than 8 story points so to provide a better estimate
  2. Add points to story B's iteration to account for the error but keep story B at 3 points
  3. Assign more resources to story B to bring it in line with the estimate
  4. Re-estimate all stories including values for A, B and C

Answer(s): D



The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business.
What should the product owner have done differently?

  1. Demonstrated only the completed stories and seek stakeholder feedback
  2. Presented the budget situation and review the cost variance
  3. Reviewed the test results to gain confidence from the stakeholders
  4. Presented a demo of all the stories including the work in progress stories

Answer(s): A



The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this.
What should the team do next?

  1. Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints
  2. Add risk mitigation time to each requirement
  3. Apply the 80/20 rule, reserving 20 percent of each sprint's capacity for risk mitigation
  4. Hold all risks until they become issues, then add issue resolution tasks to the product backlog

Answer(s): A



What should a team do when they complete all sprint goals earlier than expected?

  1. Begin working on an item in the backlog
  2. Ask the scrum master to select an item from the backlog on which to work
  3. Ask the product owner to select an item from the backlog on which to work
  4. Jointly decide with the scrum master on an item from the backlog on which to work

Answer(s): C



Page 10 of 81



Post your Comments and Discuss PMI PMI-ACP exam with other Community members:

mustapha commented on August 14, 2024
good simulation
Anonymous
upvote

Ravi commented on March 28, 2024
I am from India. I wrote this exam last week and I passed. The study material is good. Saved me a lot of time. I was actually planning on a bootcamp but then I came across this site and decided to give a try. It worked out well.
INDIA
upvote

Krasen commented on June 15, 2023
Thank you for these questions and answers. The 50% discount code worked. I bouth 2 exams and I already passed one.
HONG KONG
upvote

Adam K commented on May 24, 2023
The stuff is really good. I do recommend it.
POLAND
upvote

Herath commented on March 18, 2022
I am happy to report that I passed my second exam today. Thank you guys for this helpful study package.
SINGAPORE
upvote

BBQ commented on December 30, 2021
It is a very useful information before going to your actual exam.
HONG KONG
upvote

Kristopher commented on January 27, 2019
I loved the payment part of the website. They do not ask for any personal information. Just the credit card number and date. Very desecrate. I like!
UNITED KINGDOM
upvote

Ivan Cheung commented on August 23, 2016
The material is useful and save me a lot of time to get the exam passed without any difficulty!!
HONG KONG
upvote