After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.
What should the product owner do to resolve this?

  1. Ask the development team to address the issue since it is in their domain
  2. Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan
  3. Meet with the team and stakeholders to address rework and rewrite stories as needed
  4. Cancel the current sprint, and meet with stakeholders to reassess the project's validity

Answer(s): C



A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories.
What should be proposed to the team?

  1. Have other team developers attend training to learn database skills
  2. Monitor the retrospectives of two additional sprints before taking action
  3. Plan fewer stories for the sprint to reduce the database engineer's workload
  4. Ask the scrum master to work the product owner to remove backlog stories that have database dependency

Answer(s): A



An agile project has three more iterations before the release. There is lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.
What should the project leader do?

  1. Encourage the team to self-organize and determine how to best complete their existing work and this spike
  2. Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal
  3. Direct the team to defer the spike until the next release and add the action on the backlog for prioritization
  4. Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration

Answer(s): C



While attending a conference, an agile practitioner learns of a new user interface (UI) framework that could benefit the team.
What should the agile practitioner do next?

  1. Identify a team member to do a proof of concept using this framework
  2. Email the team directing them to immediately begin using this new framework
  3. Obtain feedback from team members on the new framework, and then suggest that the product owner create a backlog item to do a spike on it
  4. Discuss this option at the next retrospective

Answer(s): C



Page 42 of 81



Post your Comments and Discuss PMI PMI-ACP exam with other Community members:

mustapha commented on August 14, 2024
good simulation
Anonymous
upvote

Ravi commented on March 28, 2024
I am from India. I wrote this exam last week and I passed. The study material is good. Saved me a lot of time. I was actually planning on a bootcamp but then I came across this site and decided to give a try. It worked out well.
INDIA
upvote

Krasen commented on June 15, 2023
Thank you for these questions and answers. The 50% discount code worked. I bouth 2 exams and I already passed one.
HONG KONG
upvote

Adam K commented on May 24, 2023
The stuff is really good. I do recommend it.
POLAND
upvote

Herath commented on March 18, 2022
I am happy to report that I passed my second exam today. Thank you guys for this helpful study package.
SINGAPORE
upvote

BBQ commented on December 30, 2021
It is a very useful information before going to your actual exam.
HONG KONG
upvote

Kristopher commented on January 27, 2019
I loved the payment part of the website. They do not ask for any personal information. Just the credit card number and date. Very desecrate. I like!
UNITED KINGDOM
upvote

Ivan Cheung commented on August 23, 2016
The material is useful and save me a lot of time to get the exam passed without any difficulty!!
HONG KONG
upvote