During a team meeting, members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks, which has lowered motivation.
What should the agile practitioner do?

  1. Organize a team-building activity to improve team morale
  2. Have team members work in pairs to learn from each other and develop new skills
  3. Ask team members to perform a value stream analysis of their activities
  4. Add more resources to the team to help with tasks

Answer(s): C



An agile team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope, the team plans to work only on spike user stories for the next three sprints.
What should an agile coach do in this situation?

  1. Ensure that the spikes identify the risks early in the project to increase the chances of success
  2. Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints
  3. Recommend that, in the first sprint, user stones with higher priority be executed in addition to the spike
  4. Support the decision, because release planning will be improved, and the product backlog can be better groomed after all spikes are executed

Answer(s): A



How can an agile team working on a new product ensure alignment with external stakeholders?

  1. Ask the product owner to provide a detailed product specification document
  2. Conduct story-mapping exercises to clarify deliverables and release priorities
  3. Hold a kick-off meeting to assign roles and responsibilities
  4. Work with the scrum master and stakeholders to ensure agile principles are followed

Answer(s): B



What can an agile team use to prioritize stories?

  1. Planning poker technique
  2. Weighted average calculation
  3. Risk-value quadrant
  4. INVEST scale

Answer(s): C



During a daily stand up, the tester engages the developer in a discussion about what will be tested during unit testing versus regression testing.
What should the scrum master do?

  1. Ask the tester and developer to discuss it after the meeting, since it is not a part of the daily stand up
  2. Encourage the discussion to resolve impediments
  3. After the meeting, escalate this issue to the tester's supervisor to ensure that this does not reoccur
  4. Ask more questions about the testing techniques to obtain clarification on team efforts for quality improvements

Answer(s): A



Viewing page 25 of 66
Viewing questions 121 - 125 out of 508 questions


Post your Comments and Discuss PMI PMI-ACP exam prep with other Community members: