A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories.What should be proposed to the team?
Answer(s): A
An agile project has three more iterations before the release. There is lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.What should the project leader do?
Answer(s): C
While attending a conference, an agile practitioner learns of a new user interface (UI) framework that could benefit the team.What should the agile practitioner do next?
The agile practitioner has determined that two different team members are working on addressing the same major issue on the project.How should the agile practitioner address this?
Answer(s): D
An executive requests information regarding a sprint status.What action should the product owner take?
Answer(s): B