PMI Agile Certified Practitioner Questions 161–165 (page: 34)

Updated On: 10-Feb-2026

A team is creating a highly marketed, time-sensitive product. The agile coach is concerned that anything other than exceptional quality will result in bad publicity for the company.
What should the agile coach ensure that developers do?

  1. Establish pair programming partners, and regularly perform peer reviews
  2. Perform demos at the end of each iteration
  3. Send coding to the quality assurance (QA) team upon completion
  4. Demonstrate each feature to the client as soon as coding is complete

Answer(s): B



During mid-sprint changes, an agile facilitator meets with the executive and development teams. During the meeting, executive team members resolve conflicts, and on their own initiative, review the iteration charts to discuss changes to the iteration's functional goal.
What practice is the agile facilitator implementing?

  1. Building openness and transparency on the project's health and status
  2. Facilitating conflict resolution among executive team members
  3. Using active stakeholder involvement to build features in an increment and iterative approach
  4. Seeking continuous feedback from executive team members

Answer(s): D



What can a team use to prioritize stories?

  1. MoSCoW method
  2. Planning poker technique
  3. Weighted average calculation
  4. INVEST scale

Answer(s): A



Business stakeholders of an agile project frequently skip the review meetings.
What should the agile practitioner do?

  1. Ask the product owner to inform all stakeholders about the project's progress
  2. Send meeting notes to all stakeholders after each review meeting
  3. Include the results of the review meetings in the information radiators
  4. Convince the stakeholders of the benefits of attending the review meetings

Answer(s): D



After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.
What should the product owner do to resolve this?

  1. Ask the development team to address the issue since it is in their domain
  2. Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan
  3. Meet with the team and stakeholders to address rework and rewrite stories as needed
  4. Cancel the current sprint, and meet with stakeholders to reassess the project's validity

Answer(s): C



Viewing page 34 of 66
Viewing questions 166 - 170 out of 508 questions