A team using Kanban identifies that their cycle time has significant variation. After brainstorming, the team determines that the root cause is the stories' varying sizes and risks.What should the team do?
Answer(s): C
Two similar stories, A and B, are estimated at 3 story points. Story C, estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.What should the agile practitioner do?
Answer(s): D
The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business.What should the product owner have done differently?
Answer(s): A
The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this.What should the team do next?
What should a team do when they complete all sprint goals earlier than expected?