Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated.

Thomas agrees, but now he has to update what document in his project management plan?

  1. Project calendar
  2. Activity attributes
  3. Resource calendar
  4. Schedule management plan

Answer(s): A

Explanation:

The project calendar needs to be updated to reflect the 24-hour time period rather than the 8-hour time period.
The project calendar is used to define the working and nonworking days and times for tasks. This calendar is usually used to represent an organization's traditional working hours. Project uses this calendar to schedule tasks that do not have resources assigned or that have a task
type of fixed duration. By default, the Standard base calendar is used as the project calendar. A user can also reflect alternative schedules by using other base calendars.
The working days and hours in the project calendar reflect the working days and hours for the whole project. A user can also specify special days off, such as company holidays. A user can also indicate other nonworking times to reflect periods when the whole team will be working
on nonproject activities, such as company meetings or department retreats.
Answer option D is incorrect. The schedule management plan will reference to the project calendar and the resource calendar. It does not need to be updated directly as a result of the time period change.
Answer option C is incorrect. The resource calendar does not need to be updated as this document defines when resources are available.

Answer option B is incorrect. The activities of the project are not changing, only the time periods of the project calendar.



You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following information except for which one?

  1. Stakeholder classification
  2. Project management team's classification
  3. Assessment information
  4. Identification information

Answer(s): B

Explanation:

The stakeholder register does not contain the project management team's classification information. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses
how they are involved in the project and identifies what role they play in the organization. The information in this document can be very perceptive and is meant for limited exchange only. It also contains relevant information about the stakeholders, such as their requirements, expectations, and influence on the project.
Answer options D, C, and A are incorrect. These are the parts of the stakeholder register.



Choose and reorder the essential steps required in developing the scheduling framework. Select an item from the right pane. Click button to move the selected item to the left pane. Click button to move the item back to the right pane. Click and buttons to sort the list, if required.

  1. See Explanation section for answer.

Answer(s): A

Explanation:




The essential steps required in developing the scheduling framework are as follows:
1.Determine how the schedule model will be developed.
2.Understand the full scope of the project.
3.Identify the project and schedule.
4.Establish project calendars and work periods.
5.Establish the optimum project update cycle.
6.Design an effective activity coding structure.

7.Determine resource planning requirements.



You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

  1. $227,140
  2. 0.75
  3. 0.95
  4. -$56,789

Answer(s): B

Explanation:

The schedule performance index is found by dividing the earned value by the planned value. In this instance, the planned value is ten percent more than where the project is forty percent of the budget at completion.
Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance.
SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula:
SPI = Earned Value (EV) / Planned Value (PV)
If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.
Answer option C is incorrect. 0.95 is the project's cost performance index. Answer options A and D are incorrect. An index is a decimal value.



Page 30 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Marv commented on October 05, 2024
This is Great!
Anonymous
upvote

Aaa commented on October 05, 2024
Best Practice
Anonymous
upvote

sadai commented on October 05, 2024
I really apricate this helpful test
Anonymous
upvote

sadai commented on October 04, 2024
I do not know to say thanks it is really useful
Anonymous
upvote

sadai commented on October 04, 2024
it was really useful thank you so much
Anonymous
upvote

sadai commented on October 04, 2024
Hi it was really helpful for me to improve my mind
Anonymous
upvote

Mohammed Haque commented on October 04, 2024
very useful site for exam prep
UNITED STATES
upvote

Melvin commented on October 04, 2024
Educational
Anonymous
upvote

NJ commented on October 04, 2024
Good Study Material
UNITED STATES
upvote

Tsholofelo commented on October 04, 2024
Mostly challenging question
Anonymous
upvote

Moana commented on October 04, 2024
Preperation
Anonymous
upvote

Nate commented on October 04, 2024
I worked really hard to pass this exam. It is a very hard exam. These questions are you best buddy. So use them.
UNITED STATES
upvote

Dominic commented on October 04, 2024
Lots of comments here asking if any one passed this exam. I did pass this exam. It is tough one. Study hard and use these exam questions and answers. You will be able to pass.
UNITED STATES
upvote

Miss Tech commented on October 04, 2024
@Lucas, hi did you pass?and how many questions were in the Exam because l can only see 47Q here on the dumps,???
Anonymous
upvote

Vani commented on October 04, 2024
Very useful
Anonymous
upvote

Priyanka Prasad commented on October 04, 2024
i need questions
Anonymous
upvote

Jack commented on October 03, 2024
are these still legit?
Anonymous
upvote

Ashok Kumar commented on October 03, 2024
Very good content to prep
UNITED STATES
upvote

User commented on October 03, 2024
By far one of the best free sources of exam dumps. I searched google for free braindumps and boom I got this right away.
UNITED STATES
upvote

Vignesh commented on October 03, 2024
I'm writing next week, are the questions still valid?
CZECH REPUBLIC
upvote

Rama commented on October 03, 2024
All looks good.
Anonymous
upvote

Yaron M commented on October 03, 2024
please stop the pain i cant take this anyomre my wife left me and she took the kids its been 54 years and i still cant pass AZ104 please make the suffering stop
Anonymous
upvote

Varon commented on October 03, 2024
The 2 hardest topics of this exams are: 1) Designing Resilient Architectures and 2) Cost-Optimized Architectures By mastering these areas, you’ll be better prepared for tricky exam questions related to resilient and cost-effective architectures.
INDIA
upvote

Haji Momen commented on October 03, 2024
The questions in the exam dumps are pretty same as the real exam the only problem is that it is not complete or has less questions compared to full version. I am from South Africa and this is expensive for me. So I will be using the free version.
South Africa
upvote

Saurabh commented on October 03, 2024
Super Course to go ahead
INDIA
upvote

solla maaten commented on October 03, 2024
just reviewing
Anonymous
upvote

DJ commented on October 03, 2024
This dump is still valid?
MALAYSIA
upvote

senan commented on October 03, 2024
salam bu ne suallardi bele
AZERBAIJAN
upvote

Rk commented on October 03, 2024
Good content
Anonymous
upvote

George commented on October 02, 2024
Focus on mastering designing scalable, resilient architectures and cost-optimization strategies using core AWS services for this SAA-C03 exam.
UNITED STATES
upvote

Esmaiel commented on October 02, 2024
This is a very good practice paper to get ready for exam. Helpful to me.
UNITED STATES
upvote

Fawad commented on October 02, 2024
The exam turned out to be very hard as stated by some users here. So there is no way to pass it unless you know the questions. And note that some of the answers in this exam dump PDF is not correct but the questions are legit.
EUROPEAN UNION
upvote

Moataz commented on October 02, 2024
I approve this exam dump. It is valid in UAE. I passed the test.
UNITED ARAB EMIRATES
upvote

JB commented on October 02, 2024
Thanks for the study material.
Anonymous
upvote