You work as a project manager for BlueWell Inc.
Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

  1. Project Schedule Management Plan
  2. Project Staffing Management Plan
  3. Project Human Resources Management Plan
  4. Project Communications Management Plan

Answer(s): B

Explanation:

The project staffing management plan will define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team.
The staffing management plan is part of human resources plan. It is a subsidiary plan of the overall

project management plan and defines
when project team members will be brought onto and released from the project. It describes when and how human resource requirements
will be met. Depending upon the needs of the project, it can be formal or informal, highly detailed or broadly framed. The staffing management
plan may include the following items: Staff acquisition, resource calendars, staff release plan, training needs, recognition and rewards,
compliance, and safety.

Answer option D is incorrect. The communications management plan defines project communication requirements and expectations.

Answer option C is incorrect. This is not a valid project management plan.


Answer option A is incorrect. The project schedule management will define when resources are needed and scheduled. But it will not define how resources are allowed to be released from the project.



Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence over the project, their interest in project, and an assessment of methods.
What can Bonnie create to gain support from the stakeholders in her project?

  1. Stakeholder identification tools
  2. Expert judgment
  3. Stakeholder Analysis Matrix
  4. Communications management plan

Answer(s): C

Explanation:

A stakeholder analysis matrix is a simple table that identifies stakeholders, their attitude towards the project, their perceived threats and concerns, and strategies the project manager can use to gain stakeholder support and remove obstacles.

Answer option A is incorrect. Stakeholder identification tools are not a precise answer for this question.

Answer option D is incorrect. The communications management plan is a broad plan and may reference the stakeholder analysis matrix, but it
is not the best answer for this question.

Answer option B is incorrect. In some cases the project manager could rely on expert judgment, but in all projects the project manager can
use a stakeholder analysis matrix.



You are the project manager for your organization. Your project will need four electrical engineers

for the project though there are no electrical engineers within your department. This scenario is best described as which one of the following terms?

  1. Assumption
  2. Risk
  3. Resource requirement
  4. Resource constraint

Answer(s): C

Explanation:

This is an example of a resource requirement. The project needs four electrical engineers even though the resources are not within your department. Your organization could be a matrix structure, or it could hire resources from outside the organization.
Answer option D is incorrect. A resource constraint is evident when the project requires the electrical engineer and she is not available. A
requirement, as in this scenario, is simply the identification of the needed resource even if the resource is not available in your department.

Answer option B is incorrect. This is not an example of a risk, unless the resource is constrained by other projects, schedules, or work and may
not be available at all when needed.

Answer option A is incorrect. An assumption would be believing the resource is available for the project without confirming the availability of
the resource.



Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project scope changes into the activity list. Where else should Robert reflect these project changes?

  1. Project final report
  2. Scope baseline
  3. Quality control mechanism
  4. Cost baseline

Answer(s): B

Explanation:

All scope changes should also be updated in the project scope baseline. The scope baseline is the project scope statement, work breakdown structure (WBS), and the WBS dictionary.
Answer option D is incorrect. If the changes affect cost then the cost baseline would also be updated. The question did not indicate that
therbe would a change in the project cost.

Answer option C is incorrect. Quality control does not change. It always reflects the demands of the project scope.


Answer option A is incorrect. The project final report evaluates the success and failures of the project scope.



Page 35 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Dipu commented on November 19, 2024
Awesome and really good questions to pass the exam if we lean the Solution details
Anonymous
upvote

David commented on November 19, 2024
Good challenge for preparation and readyness
CANADA
upvote

R commented on November 19, 2024
Best for practice
Anonymous
upvote

Esther commented on November 19, 2024
The content walks you through all parts of the exams and covers what is in actual exam. I passed today.
UNITED KINGDOM
upvote

Mosa commented on November 18, 2024
This site gives the questions and then gives you the answers. I saw a big number of these questions in my exam. The dump is valid in India.
INDIA
upvote

Alankruta commented on November 18, 2024
Good set of questions
Anonymous
upvote

Akku commented on November 18, 2024
Good for AI certification prep
Anonymous
upvote

Muhammad Ali commented on November 18, 2024
It is really helping
Anonymous
upvote

vk commented on November 18, 2024
nice set of questions
UNITED STATES
upvote

Viqas commented on November 18, 2024
My exam is coming up which I heard they are notorious for being very tricky/difficult. I don't know how good or close these questions are to real exam. But I see a lot of positive comments and tons of users talking about it. I cross my fingers.
UNITED STATES
upvote

Mini-Pritz commented on November 18, 2024
AI is the way to go these days and this certification exam which I passed today should help my with some carrier boost.
UNITED STATES
upvote

Harish commented on November 18, 2024
It is very helpful to understand the GCP
Anonymous
upvote

Gopikrishna commented on November 17, 2024
Its Going Good
INDIA
upvote

yoga commented on November 17, 2024
goood i cann guys
Anonymous
upvote

Peace commented on November 17, 2024
questions are helpful
Anonymous
upvote

Ahmed Mansour commented on November 17, 2024
Good mind set
Anonymous
upvote

Pretty commented on November 17, 2024
This have been really helpful thank you so much
Anonymous
upvote

pretty commented on November 17, 2024
Helpful thanx
Anonymous
upvote

Morad commented on November 17, 2024
So many new questions in this version. Thank you for providing the updated version.
Turkey
upvote

Md. Jakir Hossain commented on November 17, 2024
pls help me given total question
BANGLADESH
upvote

Feroz commented on November 17, 2024
These questions are very similar to the exam question. Thank you for this great test dumps!
Anonymous
upvote

Mohamed commented on November 17, 2024
No Comments
Anonymous
upvote

shakila commented on November 16, 2024
how to start i m begginer
Anonymous
upvote

peter commented on November 16, 2024
I'm finding these question helpful
Anonymous
upvote

Kris commented on November 16, 2024
Nice Questions
Anonymous
upvote

Folarin commented on November 15, 2024
Nice content, hope to take my exam soonest
Anonymous
upvote

Dag Alytus commented on November 15, 2024
This is helpful
UNITED STATES
upvote

Priscilla commented on November 15, 2024
I'm waiting for more questions
Anonymous
upvote

togdheer commented on November 15, 2024
good revision resource
UNITED STATES
upvote

Mohammed commented on November 15, 2024
After checking these questions and reviewing all the answers and Explanations I realized that I would not have been able to pass the exam based on my current knowledge. This is completely changed my approach in how I am going to prepare now.
UNITED STATES
upvote

Makhmoor commented on November 15, 2024
please make it free
EUROPEAN UNION
upvote

Ardi commented on November 14, 2024
its a great platform to upskilling your knowledge about blockchain
Anonymous
upvote

Quentin commented on November 14, 2024
I noticed that some comments were related to answers not being 100% correct. But for me as long as questions are real and same as the actual exam I was okay.
Mexico
upvote

kagelelo commented on November 14, 2024
how do you pass the ged science test
Anonymous
upvote