Free PMI-SP Exam Braindumps (page: 36)

Page 36 of 82

You work as a project manager for Blue Well Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30.
What does this figure depict?

  1. Project is behind the schedule.
  2. Costs are higher than planned.
  3. Costs are right on target.
  4. Costs are lower than planned.

Answer(s): D

Explanation:

According to the question, the cost variance of the project is 30, which is a positive figure. A positive value means that cost is less than planned.
What is CV?
Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are higher than budgeted
or lower than budgeted. The cost variance is calculated based on the following formula:
CV = Earned Value (EV) - Actual Cost (AC)
A positive value means that spending is less than budgeted, whereas a negative value indicates that costs are higher than
originally planned for the project.

Answer option C is incorrect. If the CV is zero, it shows that cost is right on target.
Answer option A is incorrect. This result is depicted by viewing the schedule variance (SV), not the CV.

Answer option B is incorrect. If the CV is a negative value, it depicts that the costs are higher than planned.



You are the project manager for your organization. You are working with your project team to define the project network diagram. Several of the activities in the project schedule appear to have external constraints. Who among the following determines which dependencies are external to the project?

  1. Project team
  2. Project sponsor
  3. Project manager
  4. Project management team

Answer(s): D

Explanation:

The project management team defines which activities are external to the project. An external dependency is any nonproject activity that is external to the project but has a direct impact on the project activities. An external
dependency may be an inspector or any agency that may have to give prior approval before the project can move forward. These
dependencies are external to the organization and are determined by the project management team to find which dependencies are external
all through the process of sequencing the activities.

Answer option C is incorrect. The project manager may be part of the project management team, but this is not the best choice.

Answer option A is incorrect. The project team does not define this relationship.


Answer option B is incorrect. The project sponsor would not define the external dependencies.



You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:



Based on this figure, what is the critical path of this project?

  1. ABEHJ
  2. ACFIJ
  3. ADGJ
  4. ACFGJ

Answer(s): D

Explanation:

The activity nodes of path ACFGJ equals 26 days and is the longest path to completion - it is the critical path.
ACFGJ= A(4)+C(8)+F(4)+G(6)+J(4)=26
What is a critical path?
A critical path is the sequence of project activities, which add up to the longest overall duration. This

determines the
shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned
project completion date (i.e. there is no float on the critical path). A project can have several, parallel, near critical paths. An
additional parallel path through the network with the total durations shorter than the critical path is called a sub-critical or
non-critical path.
These results allow managers to prioritize activities for the effective management of project completion, and to shorten the

planned critical path of a project by pruning critical path activities, by "fast tracking" (i.e., performing more activities in
parallel), and/or by "crashing the critical path" (i.e., shortening the durations of critical path activities by adding resources).

Answer option A is incorrect. ABEHJ takes only 22 days to complete; it is not the critical path.
ABEHJ=A(4)+B(5)+E(2)+H(7)+J(4)=22

Answer option C is incorrect. ADGJ takes only 15 days to complete; it is not the critical path.
ADGJ=A(4)+D(1)+G(6)+J(4)=15

Answer option B is incorrect. ACFIJ takes only 23 days to complete; it is not the critical path.
ACFIJ=A(4)+C(8)+F(4)+I(3)+J(4)=23



You are the project manager for your organization. Management has offered you a bonus if you can complete the project work two months earlier than what your schedule predicts. You can use a schedule compression technique, but management does not want to increase costs in the project.
What approach would you recommend to condense the project duration?

  1. Fast tracking
  2. Crashing
  3. Effort-driven activity analysis
  4. Rewards and recognition for the project team

Answer(s): A

Explanation:

Of all the choices, only fast tracking is an option that would not increase project costs. Fast tracking allows phases of the project to overlap,
but it does increase project risks.
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in
sequence. It is shortening the project schedule without reducing the project scope.
Answer option B is incorrect. Crashing adds labor to the project and increases project costs.
Answer option C is incorrect. Effort-driven activity analysis examines activities whose duration may be reduced by adding labor. This approach,

however, increases project costs, as it is a form of project crashing.
Answer option D is incorrect. Rewards and recognitions are good incentives for the project team, but simply offering the reward does not
decrease the duration of the project.



Page 36 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Venkat commented on September 27, 2024
Preparing for certification
Anonymous
upvote

Nigel commented on September 27, 2024
Managed to pass my exam bu using the full version of this exam. This free version has less questions compared to PDF.
Spain
upvote

Kangaroo Jack commented on September 27, 2024
The best way to study and pass your exam. Quick and painless. The full PDF version is well worth the money.
AUSTRALIA
upvote

Ouahid commented on September 27, 2024
Thank you, it is very useful
AUSTRIA
upvote

Karlik commented on September 27, 2024
I passed the exam with help from this questions :)
Anonymous
upvote

Nate commented on September 27, 2024
Has anyone recently taken the exam? Can anyone confirm these questions are similar or word for word?
Anonymous
upvote

Birkha commented on September 27, 2024
NO comments
BHUTAN
upvote

raba commented on September 26, 2024
@khorshal can i use this alone to pass the exams
Anonymous
upvote

raba commented on September 26, 2024
some of the questions are straight forward
Anonymous
upvote

Judwa commented on September 26, 2024
This exam is super hard. I was overwhelmed. After using this exam dump, I went into the exam feeling a bit better. I passed my test. :-)
INDIA
upvote

Jubran commented on September 26, 2024
Clear explanations and well-structured content made it so much easier to prepare and pass.
UNITED STATES
upvote

KXK commented on September 26, 2024
The study guide was concise yet comprehensive. It helped me focus on the key topics and feel more prepared than ever!
INDIA
upvote

Chandra commented on September 26, 2024
I passed my exam with ease, thanks to the targeted material in this guide. It made a huge difference in how I prepared.
CANADA
upvote

raba commented on September 26, 2024
I was thinking question 16 should be a legacy systems
Anonymous
upvote

Bubba commented on September 26, 2024
Good work guys. The layout is user-friendly, and the content is spot on.
Hong Kong
upvote

rabihu commented on September 26, 2024
These are really challenging questions.i love it
Anonymous
upvote

Murad commented on September 26, 2024
This guide gave me the exact focus I needed to pass my exam on the first try. Highly effective and reliable.
Turkey
upvote

raba commented on September 26, 2024
these are really good questions
Anonymous
upvote

Kg commented on September 26, 2024
hi @phil , thank you for the response , basically i must just check wether the answers are correct
Anonymous
upvote

Alhassan commented on September 26, 2024
these are really good questions
Anonymous
upvote

Jose commented on September 26, 2024
these are really good questions
Anonymous
upvote

David commented on September 26, 2024
good Questions
Anonymous
upvote

Mohammed commented on September 26, 2024
Absolutely grateful for this exam dumps. Passed on the first set down.
France
upvote

Phil commented on September 26, 2024
Hi @kg I feel you. Based on my experience, the questions are valid but some of the answers were not accurate. So I managed to study and kinda figure these answers. For me the accuracy of the questions were more important and I saw most of them in the exam.
Anonymous
upvote

Madhan commented on September 26, 2024
Useful questions
INDIA
upvote

Owol Sentmi commented on September 26, 2024
great Questions
Anonymous
upvote

Noha commented on September 26, 2024
Feeling very confident now. Went over the free questions here then decided to buy the full PDF and test engine with the sale price and now ready to write my test. Will share my experience next week after I go for my exam. Wish me luck guys.
UNITED STATES
upvote

Baylis commented on September 26, 2024
I am certified now. Thank you team.
UNITED STATES
upvote

Harper commented on September 26, 2024
If you have access to full version of this exam dumps then you are good to go and pass your exam.
EUROPEAN UNION
upvote

Suil commented on September 26, 2024
Very good Practice questions
CHINA
upvote

lala commented on September 26, 2024
really helping
Anonymous
upvote

Champ commented on September 26, 2024
Good to see that something is still free. I truly appreciate this service.
Mexico
upvote

kg commented on September 26, 2024
anyone who sees this comment please respond to my question, can the answers on freedumps be trusted , because im using different materials also from exam topics and the answers dont look the same
Anonymous
upvote

Shams commented on September 25, 2024
This exam is valid in UAE. I passed.
UNITED ARAB EMIRATES
upvote