John is the project manager for his organization. Management has asked John to fast track his project in order to reach a particular date for the project completion.
When John fast tracks the project what project management component must be updated to reflect this decision? Choose the best answer.

  1. Organizational process assets
  2. Cost management plan
  3. Resource calendars
  4. Risk register

Answer(s): D

Explanation:

Fast tracking allows phases of the project to overlap and increases risk for the project.
When new risks are introduced into the project they
should be recorded in the risk register.
Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning.
Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified
risks are put in the risk register.

Answer option B is incorrect. The costs do not change because of the new fast tracking requirement.
Answer option C is incorrect. Resource calendars show the availability of project resources.
Answer option A is incorrect. Organizational process assets are updated as a result of updating the risk register when you consider that the
risk register will become part of the organizational process assets. However, this is not the best answer for this question.



You are the project manager of the NHQ Project and are trying to determine which seller you should

choose for the project. You have received proposals from six vendors and they are all very good proposal, qualified to complete the project work, and the prices are close to the same. You would like to create method of ranking each vendor based and assign a score value to several different categories. Because the project is a high-profile project, you have assigned 25 points to experience and 10 points for all of the other categories to judge the vendors. This is considered what type of source selection process?

  1. Screening system
  2. Preferred vendor list
  3. Benefits-cost analysis
  4. Weighting system

Answer(s): D

Explanation:

This is an example of a weighting system as the values you're measuring are weighted towards experience.

Answer option B is incorrect. A preferred vendors list describes the vendors you're allowed to choose from in the organization.

Answer option A is incorrect. A screening system sets qualifiers in place, such as the vendor must have a PMP on staff, in order to qualify for
the project.

Answer option C is incorrect. The benefits-cost analysis defines the total number of benefits to the number of costs the project requires. .



Frank is the project manager in BlueWell Inc. He is working with his project to subdivide the project work packages into smaller, more manageable components. He and the project team are planning in detail all of the things the team will need to create, purchase, or do in order to satisfy the project scope. Management is concerned with the activity which Frank is using in this scenario, as they believe that Frank is taking too long to complete this pre-execution activity.
Which of the following techniques of the activity process is Frank using in this example?

  1. Rolling wave planning
  2. Expert judgment
  3. Creating a project template
  4. Decomposition

Answer(s): D

Explanation:

This is an example of decomposition. Frank and the project team are subdividing the work packages into smaller, more manageable units
called activities.
The tools and techniques used in defining the activity process are as follows:
Decomposition: It is used to further divide the project work package into a more smaller and convenient form called activities.
Rolling Wave Planning: It is a form of progressive elaboration planning where the work to be

accomplished in the near term is planned
in detail and future work is planned at a higher level of WBS. Templates: It is an activity list or a part of the activity list taken from the previous project and used in a new project.
Expert Judgement: The skilled members in a project team or other experts who develop project scope statements can help provide
knowledge in defining activities.



Kelly is the project manager of her organization. She is reviewing the project network diagram to confirm that the resource she has identified is available to complete the project assignments without conflicting with other activities in the project node. The availability of resources will help Kelly determine the final finish date for the project.
What scheduling technique is Kelly using?

  1. Critical Chain method
  2. Resource utilization
  3. Critical Path method
  4. Resource leveling heuristics

Answer(s): A

Explanation:

The Critical Chain method examines the availability of project resources to determine when the resource may be utilized without conflicting
with other activities.
The Critical Chain method is a project management technique in which schedule network analysis is used for the purpose of modifying and
determining a set of project schedules to account for more inadequate than estimated project financial resources. This method tends to keep
the resources levelly loaded, but requires the resources to be flexible in their start times and to quickly switch between tasks and task chains
to keep the whole project on schedule. In the Critical Chain method, projects are completed more rapidly and with better scheduling
consistency.

Answer option C is incorrect. The Critical Path method examines the duration of the critical path to determine the finish date for the project. It
does not consider when project activities are available.
Answer option B is incorrect. Resource utilization simply means that the resource is scheduled for work.

Answer option D is incorrect. A resource leveling heuristic is a guideline, such as a maximum of 35 hours per week, per resource. It is a rule

that usually signals the maximum amount of hours a resource may be utilized on the project.



Page 41 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Lakshminarsimhan.R commented on November 23, 2024
The questions and answers are good in this portal, kindly please add comments as well for answers, so that it will be very hepful.
Anonymous
upvote

Naredn commented on November 22, 2024
Best practices at one place
Anonymous
upvote

max commented on November 22, 2024
thanks, i appreciate it
CANADA
upvote

Fefe commented on November 22, 2024
Great so far
Anonymous
upvote

sami commented on November 22, 2024
is the quation real exam?
GERMANY
upvote

sami commented on November 22, 2024
is The Quation from real exam or not
GERMANY
upvote

sam commented on November 22, 2024
practice for cad
RESERVED
upvote

James commented on November 21, 2024
I love this
CANADA
upvote

siii commented on November 21, 2024
great resources for exam
INDIA
upvote

Tom commented on November 21, 2024
Can anyone confirm if these questions are still valid?
SOUTH AFRICA
upvote

Harshit Soni commented on November 21, 2024
Good explanation
INDIA
upvote

Devopsengineer commented on November 21, 2024
review my knowledge to take an exam
UNITED STATES
upvote

gopu singh commented on November 21, 2024
ok ok ok ok
INDIA
upvote

huiyi commented on November 21, 2024
Great dumps to practice
Anonymous
upvote

Harshit Soni commented on November 21, 2024
Questions looks technical and authentic
INDIA
upvote

FN commented on November 21, 2024
Great work team!
ITALY
upvote

raj commented on November 20, 2024
it is good comare to other sites
Anonymous
upvote

bpop commented on November 20, 2024
@Patak when did you take the exam?
UNITED STATES
upvote

Rab commented on November 20, 2024
Useful reference
Anonymous
upvote

Pallavi commented on November 20, 2024
Preparing for certification
EUROPEAN UNION
upvote

John Okediji commented on November 20, 2024
I like it. It's helping me prepare well for my exam.
Anonymous
upvote

aam commented on November 20, 2024
great lesson
Anonymous
upvote

Ajay commented on November 20, 2024
Best exam questions & answers
Anonymous
upvote

Diago commented on November 19, 2024
Unless you use these so called exam dumps to prepare for your exam you are not going to be able to pass your exam. The questions are tricky, confusing and very hard.
Brazil
upvote

Soman commented on November 19, 2024
Hay Guys, I just got my first certificate. This exam dumps worked well... but I also studied prior to coming across this site.
UNITED KINGDOM
upvote

Mike commented on November 19, 2024
In my opinion, they work well for me, but it depends on how you approach them. My method isn't about memorizing the exact questions and answers from the practice tests to use on the real exam. Instead, I focus on understanding why I got certain questions wrong so I can deepen my comprehension of the material.
EUROPEAN UNION
upvote

Mohan commented on November 19, 2024
I did not want to not to book my test and walk into a test center without being prepared as this exam is very hard. So I studied and used the full/paid version of these questions and passed my exam.
India
upvote

Shu commented on November 19, 2024
Considerably good.
UNITED STATES
upvote

Ji commented on November 19, 2024
Gute Vorbereitung auf DITS
GERMANY
upvote

EdvinO commented on November 19, 2024
Took the test today and passed. I learned a lot from practicing these questions
NETHERLANDS
upvote

Person McPersonface commented on November 19, 2024
Just took the exam. Many of these questions are on it. Best to study this hard!
FRANCE
upvote

Dior commented on November 19, 2024
Hi i'm about to pass my exam this week and hope that it will work for meD
Anonymous
upvote

Dipu commented on November 19, 2024
Awesome and really good questions to pass the exam if we lean the Solution details
Anonymous
upvote

David commented on November 19, 2024
Good challenge for preparation and readyness
CANADA
upvote