Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed.
What does Anna want to create in this instance?

  1. Power/interest grid
  2. Salience model
  3. Power/influence grid
  4. Communications matrix

Answer(s): A

Explanation:

Anna needs to create a power/interest grid. This grid groups the stakeholders based on their level of authority and level of concern regarding
the project outcomes.
The power/interest grid forms a group of the stakeholders based on their level of authority (power) and their level of interest in the project.
Interest accounts to what degree the stakeholders are affected by examining the project or policy change, and to what degree of interest or
concern they have about it. Power accounts for the influence the stakeholders have over the project or policy, and to what degree they can
help to accomplish, or block, the preferred change.

Stakeholders, who have high power and interests associated with the project, are the people or organizations that are fully engaged with the project.
When trying to generate strategic change, this community is the target of any operation.
Answer option B is incorrect. A salience model classifies stakeholders based on their power, urgency, and legitimacy.

Answer option C is incorrect. A power/influence grid groups the stakeholders based on their power and influence.

Answer option D is incorrect. A communications matrix simply maps which stakeholder need to communicate with other stakeholders.



You work as the project manager for Blue Well Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a trainee, has a doubt related to the inputs of monitor and control project work.
Which of the following is the input to monitor and control project work?

  1. Project document updates
  2. Expert judgment
  3. Performance report
  4. Project management plan updates

Answer(s): C

Explanation:

Performance report is an input of monitor and control project work. Reports are prepared by the project team detailing activities, milestones,
and problems.
A performance report is made by the project team detailing activities, milestones, problems, accomplishments, and identified issues.
Performance reports are used to report some key information as follows:
Current status
Scheduled activities
Significant accomplishment for the period
Forecasts
Issues

Answer option B is incorrect. It is the tool and technique used for monitoring and controlling project work.
Answer options A and D are incorrect. These are the outputs to monitor and control project work.



You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project.
Which of the following statements is most accurate about fast tracking the project?

  1. Fast tracking only works if activities can be overlapped to shorten duration.
  2. Fast tracking only works if the activities are effort-driven.
  3. Fast tracking only works if the activities are resource-driven.
  4. Fast tracking only works if activities can have start-to-start relationships.

Answer(s): A

Explanation:

Fast tracking is only valid if the activities or phases can be overlapped. Some activities or phases cannot be overlapped due to mandatory dependencies in the project. In other words, the work must be completed in a particular given order.
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in
sequence. It is shortening the project schedule without reducing the project scope.
Answer option C is incorrect. This is not a valid description of fast tracking.
Answer option B is incorrect. Effort-driven or activities of fixed duration can be fast tracked.
Answer option D is incorrect. The relationships among the activities do not have to be start-to-start to be fast tracked.



Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

  1. Mandatory dependencies
  2. Required dependencies
  3. Discretionary dependencies
  4. External dependencies

Answer(s): D

Explanation:

An external dependency is any nonproject activity that is external to the project but has a direct impact on the project activities. An external dependency may be an inspector or any agency that may have to give prior approval before the project can move forward.

Answer option B is incorrect. Required dependency is not a valid term to describe a dependency.
Answer option A is incorrect. Mandatory dependencies describe the required order in which the project work must take place - such as
foundation before framing, or the operating system installed before the application may be installed.

Answer option C is incorrect. Discretionary dependencies describe the optional order of the project work, such as painting the walls before
installing the carpet.



Page 43 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

George commented on October 30, 2024
Thanks for all the assistance i got the full PDF version. Highly recommended!
UNITED STATES
upvote

Arthur commented on October 30, 2024
If you're preparing for the AZ-104 exam, I highly recommend checking out these questions. They offer great resources and practice questions that can really help you understand the material and boost your confidence. Good luck with your studies!
UNITED STATES
upvote

RM commented on October 30, 2024
Thank you for the dumps
Anonymous
upvote

Dayanidhi M commented on October 29, 2024
good exam dump
Anonymous
upvote

Vulquin commented on October 28, 2024
Hello, I wanted to take the pdf version for az-140 certification and I can't find where to buy it.
Anonymous
upvote

yassmine commented on October 28, 2024
good questions
Anonymous
upvote

PP commented on October 28, 2024
Good!! please!!
KOREA REPUBLIC OF
upvote

Nevel commented on October 28, 2024
This is my Go-to site for passing my cert exams. So fart I have passed 2 exams with these dumps. So great respect!
UNITED KINGDOM
upvote

Anthony commented on October 28, 2024
good content
Anonymous
upvote

Sree commented on October 27, 2024
Good dump questions
Anonymous
upvote

Nmathew commented on October 27, 2024
Similar questions for qdba 2024
UNITED KINGDOM
upvote

Trang commented on October 27, 2024
Very helpful
JAPAN
upvote

Rakesh Debnath commented on October 27, 2024
Nice sample questions
UNITED STATES
upvote

Arvind Sharma commented on October 27, 2024
Helpful questions for preparation foe LA exam
Anonymous
upvote

Teji commented on October 26, 2024
Good Practice Questions before appearing to exams
Anonymous
upvote

Preston commented on October 26, 2024
Hope everyone is having a wonderful day. I am because I just passed my exam. Sharing my insight... this exam dump has lots of questions from the real exam. But the exam is not easy. So I need to say that you must study hard to pass.
UNITED STATES
upvote

Alex Z commented on October 26, 2024
Great insight.
UNITED STATES
upvote

Rajesh Kumar M - commented on October 26, 2024
For the question 6- the continual improvement , the organization shall continually improve the suitability, adequacy and effectiveness of the QMS. Not Efficiency, Refer Clause 10.3 continual improvement in ISO 9001 :2015
Anonymous
upvote

PC commented on October 26, 2024
Good content
Anonymous
upvote

Lawrence commented on October 26, 2024
Absolutely excellent
Anonymous
upvote

ABC commented on October 26, 2024
I found these dumps are useful
INDIA
upvote

Rupa commented on October 26, 2024
Getting good practice with the qs
Anonymous
upvote

vinay commented on October 25, 2024
practice test
UNITED STATES
upvote

Shree commented on October 25, 2024
recomendeds . Thanks
Anonymous
upvote

Olympia commented on October 25, 2024
The free version is good but does not have all questions. However the PDF has double the amount of questions and very helpful to pass the exam.
Canada
upvote

Scruzer commented on October 25, 2024
Cleared this exam today. Questions are still valid.
EUROPEAN UNION
upvote

Vidhi Mishra commented on October 25, 2024
Nice set of questions
Anonymous
upvote

Srivats commented on October 25, 2024
Hello, Great learning. Thank you. Looks like Question 13's answer should be D. "If you plan to use the segment again, stop the publish schedule instead" as highlighted in doc.
Anonymous
upvote

Priest-Son commented on October 24, 2024
helpful questions also in other forums
UNITED STATES
upvote

Simon commented on October 24, 2024
guys waht do you think about this dump?
Anonymous
upvote

Kay commented on October 24, 2024
There's new test updated for network+: N10-009. Hope we could have it soon.
Anonymous
upvote

John Como commented on October 24, 2024
Very helpful
UNITED STATES
upvote

saif Ali commented on October 24, 2024
for Question no 50 The answer would be using lambda vdf as this provides automation
INDIA
upvote

Baghya commented on October 24, 2024
Yeh dumps use kiye aur exam mein pass ho gaya.
INDIA
upvote