You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms.
What type of an estimate are you creating in this scenario?

  1. Parametric estimate
  2. Definitive estimate
  3. Analogous estimate
  4. Bottom-up estimate

Answer(s): A

Explanation:

This is an example of a parametric estimate. This estimate type uses a parameter, such as four hours of painting per hotel room, and multiplies this value across the total number of units, such as 1,500 rooms. A parametric estimate is an estimate that uses a parameter to predict the costs of the project, such as cost per network drop or cost per software license. Parametric estimating technique utilizes the statistical relationship that exists between a series of historical data and a particular delineated list of other variables.
Answer option C is incorrect. An analogous estimate type uses a similar project's duration as a basis for the current project's estimate duration.
Answer option B is incorrect. A definitive estimate type accounts for the duration or costs of each work package in the WBS.
Answer option D is incorrect. A bottom-up estimate, also known as a definitive estimate, accounts for the duration or costs of each work package in the WBS.



Which organizational theory explains the factors that promote performance of people in any organization?

  1. Herzberg's theory
  2. Maslow's Hierarchy theory
  3. McGregor's theory
  4. Expectancy theory

Answer(s): A

Explanation:

Herzberg's Motivation-Hygiene Theory, also known as Two Factor Theory, was developed by Frederick Herzberg, a psychologist who found that job satisfaction and job dissatisfaction acted independently of each other. Two Factor Theory states that there are certain factors in the workplace that cause job satisfaction, while a separate set of factors cause dissatisfaction. Two Factor Theory distinguishes between the following: Motivators (e.g. challenging work, recognition, responsibility) which give positive satisfaction, arising from intrinsic conditions of the job itself, such as recognition, achievement, or personal growth. Hygiene factors (e.g. status, job security, salary and fringe benefits) which do not give positive satisfaction, although dissatisfaction results from their absence. These are extrinsic to the work itself, and include aspects, such as company policies, supervisory practices, or wages/salary. Essentially, hygiene factors are needed to ensure an employee is not dissatisfied. Motivation factors are needed in order to motivate an employee to higher performance, Herzberg also further classified our actions and how and why we do them, for example, if you perform a work-related action because you have to, then that is classed as movement, but if you perform a work-related action because you want to, then that is classed as motivation.

Answer option C is incorrect. McGregor's X and Y theory describes the team members and their behavior on the project and how management responds.
Answer option B is incorrect. It describes the five layer of needs we all have.
Answer option D is incorrect. It explains the processes that an individual undergoes to make choices.



You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?

  1. Wednesday
  2. Thursday
  3. Monday
  4. Tuesday

Answer(s): A

Explanation:

The project will end on a Wednesday. If the project work commences on a Tuesday, there will be four days to complete in that week. That will bring the project work down to 63 days of remaining work. Each work week counts as five days of work. 63 divided by 5 is 12 work weeks with three days remaining. The 63rd remaining day will complete on a Wednesday. Answer options C, D, and B are incorrect. These are not the valid answers.



Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort.
Which of the following is the best example of apportioned effort?

  1. Adding features to the project's product that is not included in the project scope.
  2. Managing the day-to-day events of a project.
  3. Creating software as defined in the project scope.
  4. Completing project activities as start-to-start events.

Answer(s): B

Explanation:

Apportioned effort is effort applied that you cannot subdivide into work packages, but it is related to, usually in a supportive role, to the completion of the project work packages. The project management overhead, such managing the project work, is an example of apportioned effort. Apportioned effort (AE) is the effort that is applied to the project-related work that cannot be easily and readily divided into discrete efforts for those tasks, but which is associated in a direct proportion to the discrete work efforts that are capable of being measured. The presence of apportioned effort relies particularly on the performance of further efforts.
Answer option C is incorrect. This is an example of discrete effort.
Answer option A is incorrect. This is an example of a scope change that has not been approved.
Answer option D is incorrect. This is an example of a scheduling technique.



You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project.

What project management process are you working with when you create a new target schedule?

  1. Estimate activity durations
  2. Estimate activity resources
  3. Control schedule
  4. Develop schedule

Answer(s): C

Explanation:

In severe cases, new schedule duration estimates with new forecasted start and finish dates are needed. In these instances, it is an example of using the control schedule process. Control schedule process is a method of monitoring the status of the project to update project progress and deal with the changes to the schedule baseline. It is concerned with: Determining the current status of the project Influencing the factors that create schedule changes Determining that the project schedule has changed Managing the actual changes as they occur Control schedule is a component of the Perform Integration Change Control process.


Answer option B is incorrect. The activity resources would only address the addition or replacement of resources needed to complete the project work.
Answer option A is incorrect. This is a tempting choice, but according to the PMBOK, new schedules are part of the control schedule process.
Answer option D is incorrect. Develop schedule is not the best choice for this question. It is a process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.