Free PMI-SP Exam Braindumps (page: 13)

Page 12 of 82

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress.
Which of the following techniques is used in generating performance reports?

  1. Work performance information
  2. Change requests
  3. Work performance measurements
  4. Forecasting method

Answer(s): D

Explanation:

Forecasting method is a technique used in generating performance reports. Forecasting is the process of estimating or predicting in unknown situations. Forecasting is about pre icting the future as accurately as possible with the help of all the information available, including historical data and knowledge of any future events that might impact forecasts. The forecasting methods are categorized as follows: Time series method: It uses historical data as the basis for estimating future outcomes. Causal/econometric method: This forecasting method is based on the assumption that it is possible to identify some factors that might influence the variable that is being forecasted. If the causes are understood, projections of the influencing variables can be made and used in the forecast.

Judgmental method: Judgmental forecasting methods incorporate intuitive judgments, opinions, and subjective probability estimates. Other methods: Other methods may include probabilistic forecasting, simulation, and ensemble forecasting. It is one of the tools and techniques of the report performance process.
Answer option A is incorrect. Work performance information is the data gathered on the status of the project schedule activities that are performed to accomplish the project work. This data is collected as part of the Direct and Manage Project Execution processes. WPI includes the following: Deliverables status Schedule Progress Costs incurred It is used as an input in generating the report performance process.
Answer option C is incorrect. Work performance measurements are created from the work performance information. WPMs are an output of Control schedule, Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs consist of planned versus actual performance indicators with respect to scope, schedule, and cost. They are documented and communicated to the stakeholders and are used to make project activity metrics, such as the following: Planned vs. Actual Technical performance and Scope performance Planned vs. Actual Schedule performance Planned vs. Actual Cost performance They are used as an input in generating the report performance process.

Answer option B is incorrect. Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules. These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that only formally documented requested changes are processed and only approved change requests are implemented. It is an output of the report performance process.



Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

  1. Procurement document
  2. Contract
  3. Business case
  4. Project statement of work

Answer(s): B,C,D

Explanation:

The Develop Project Charter process documents the formal authorization of a project or a phase. It also documents initial requirements that satisfy the stakeholder's needs and expectations. It is used to validate the decisions made during the previous iteration of the Develop Project Charter process. The various inputs of this process are as follows: Project statement of work Business case Contract Enterprise environmental factors Organizational process assets The output of the Develop project Charter process is as follows : Project charter
Answer option A is incorrect. Procurement document is the input of the Identify Stakeholders process.



Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities.
This is an example of which term?

  1. Resource calendar conflict
  2. Matrix network
  3. Organizational process assets
  4. Activity resource requirements

Answer(s): D

Explanation:

Because the activities in Beth's project require Tim and his skills. This is an example of an activity resource requirement. A resource constraint would also have been an acceptable answer.
Answer option B is incorrect. This may be a matrix organization, but matrix network is not a valid project management term.
Answer option C is incorrect. Organizational process assets are things that have been created to help assist the management of the project.
Answer option A is incorrect. A resource calendar conflict is not a valid project management term.



Fill in the blank with an appropriate phrase. The_____ allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.

  1. Schedule model

Answer(s): A

Explanation:

The main function of the schedule model is to provide useful 'road map' that can be used by the project manager and the project team to assist them in completing the project fruitfully. A well-developed schedule model is an active tool used to predict at what time the project work that remains to be completed can reasonably be completed. The schedule model allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.






Post your Comments and Discuss PMI PMI-SP exam with other Community members:

PMI-SP Exam Discussions & Posts