A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than- planned cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.
What should the project manager have done to avoid this situation?

  1. Notified all vendors about the invoicing and nonpayment deadlines
  2. Reviewed the total committed cost against the cost invoiced at project closing
  3. Involved the finance team and discussed the issue with the vendor
  4. Captured and reviewed all of the project work and related costs regularly

Answer(s): D



A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.
What should the project manager do?

  1. Fast track the project
  2. Adjust the budget
  3. Introduce a float
  4. Adjust the project time line

Answer(s): A



A project manager is working with a co-located agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to co-locate.
What should the project manager do to keep the team performing as effectively as possible?

  1. Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance
  2. Provide the team with virtual collaboration software and training on the software to minimize disruption
  3. Transition the team from an agile approach to a predictive approach for better performance control
  4. Evaluate project performance and step in if performance decreases to an unacceptable level

Answer(s): D



A project manager is reviewing the requirements of a large program.
Which requirements should the project team prioritize to avoid getting fines?

  1. Certifying sustainable products
  2. Establishing company processes
  3. Complying with new regulations
  4. Developing new product lines

Answer(s): C