In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.
What should the project manager do?

  1. Facilitate training on version control and project artifacts.
  2. Maintain separate document control via regions to avoid discrepancies.
  3. Maintain a central repository of artifacts with a version control system.
  4. Develop a document management software for version control.

Answer(s): C



A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?

  1. Work with the project manager to develop a new approach that will bring benefits to the project
  2. Suggest using an agile approach since customer and team collaboration is critical for project success
  3. Establish a project management methodology that requires the customer to provide daily updates to the team
  4. Provide a project management template for the project manager to follow as a guide

Answer(s): B



A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.
What should the project manager do?

  1. Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders
  2. Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register
  3. Communicate the risk to the steering committee and request a mitigation plan from senior management
  4. Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders

Answer(s): D



A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below.
What should the team do next?

  1. Ask the product owner if some low-priority stories could be cut from the sprint
  2. Continue with the sprint as the progress shows buffers for potential interruptions
  3. Ask the project team to select any additional stories as they have additional capacity than planned
  4. Continue with the sprint work as planned and keep monitoring

Answer(s): D