FILL BLANK
Fill in the blank with an appropriate phrase.

___________ is the study of how the variation (uncertainty) in the output of a mathematical model can be apportioned, qualitatively or quantitatively, to different sources of variation in the input of a model.

  1. Sensitivity analysis

Answer(s): A



You are the project manager of QSL project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?

  1. Predecessor and successor diagramming
  2. System or process flowcharts
  3. Cause and effect diagrams
  4. Influence diagrams

Answer(s): B



Bill is the project manager for a project that will last six months and has a budget of $580,000. In this project a high-risk has been identified with the new materials the project will be using. Bill would like to assign one person, Beth, to be responsible to monitor this risk. Bill assigns Beth the authority to respond to the risk event if it appears in the risk events that is likely to happen. In addition, Bill hires a consultant to work with Beth on this area of the project. In this instance, who is the risk response owner?

  1. Bill, because he is the project manager
  2. Beth, because she has the authority to respond to the risk event
  3. Beth and the consultant are the risk owners
  4. The consultant working with Beth, because this is transference

Answer(s): B



Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to express to her project team and to the management the importance of communication in this project. She would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

  1. 156
  2. 3,003
  3. 78
  4. 6,084

Answer(s): B



Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?

  1. Configuration management system
  2. Scope change control system
  3. Integrated change control
  4. Change log

Answer(s): C