You are the project manager of the GHY project for your organization. You are about to start the qualitative risk analysis process for the project and you need to determine the roles and responsibilities for conducting risk management. Where can you find this information?

  1. Enterprise environmental factors
  2. Risk register
  3. Risk management plan
  4. Staffing management plan

Answer(s): C



Neil works as a project manager for SoftTech Inc. He is working with Tom, the COO of his company, on several risks within the project. Tom understands that through qualitative analysis Neil has identified many risks in the project. Tom's concern, however, is that the priority list of these risk events are sorted in "high- risk," "moderate-risk," and "low-risk" as conditions apply within the project. Tom wants to know that is there any other objective on which Neil can make the priority list for project risks. What will be Neil's reply to Tom?

  1. Risks may be listed by the additional analysis and response
  2. Risk may be listed by the responses in the near-term
  3. Risks may be listed by priority separately for schedule, cost, and performance
  4. Risks may be listed by categories

Answer(s): C



Which of the following processes involves choosing the alternative strategies, executing a contingency or fallback plan, taking corrective action, and modifying the project management plan?

  1. Monitor and Control risk
  2. Configuration Management
  3. Integrated Change control
  4. Scope Change control

Answer(s): A



Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was that the software is mission-critical and must be flawless before it can be put into product. What type of a risk response has Melody used in this scenario?

  1. Mitigation
  2. Enhance
  3. Transference
  4. Avoidance

Answer(s): A



Rex is the project manager of the BDF Project. This project will last for two years and has a budget of $2,345,000. Management has instructed Rex that the project must not go over budget as funds are very tight in the organization. During the project planning Rex and the project team discover a positive risk event to save $75,000. Rex wants to make certain that this risk event happens so which risk response method is most appropriate?

  1. Share
  2. Mitigation
  3. Exploit
  4. Enhance

Answer(s): C