Fred is the project manager of the PKL project. He is working with his project team to complete the quantitative risk analysis process as a part of risk management planning. Fred understands that once the quantitative risk analysis process is complete, the process will need to be completed again in at least two other times in the project. When will the quantitative risk analysis process need to be repeated?

  1. Quantitative risk analysis process will be completed again after the cost management planning and as a part of monitoring and controlling.
  2. Quantitative risk analysis process will be completed again after new risks are identified and as part of monitoring and controlling.
  3. Quantitative risk analysis process will be completed again after the risk response planning and as a part of monitoring and controlling.
  4. Quantitative risk analysis process will be completed again after the plan risk response planning and as part of procurement.

Answer(s): C



FILL BLANK
Fill in the blank with an appropriate phrase.

___________ are activities that are dangerous to complete and manage such as construction, electrical work, or manufacturing.

  1. Pure risks

Answer(s): A



Which of the following is a risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold?

  1. Avoidance
  2. Exploit
  3. Transference
  4. Mitigation

Answer(s): D



You are the project manager for Genpact Inc. You have established quarterly risk management meetings. Which of the following is not a component of a risk management meeting?

  1. Assessing the overall status of risks in the project
  2. Review of risk responses
  3. Assessment or risk
  4. The availability of the individual

Answer(s): D



Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.


If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?

  1. $35,000
  2. $41,700
  3. $14,000
  4. $6,700

Answer(s): D



Viewing page 23 of 90
Viewing questions 111 - 115 out of 273 questions