Free RMP Exam Braindumps (page: 32)

Page 32 of 111

Your organization has a project that is expected to last 20 months but the customer would really like the project completed in 18 months. You have worked on similar projects in the past and believe that you could fast track the project and reach the 18 month deadline. What increases when you fast track a project?

  1. Resources
  2. Costs
  3. Communication
  4. Risks

Answer(s): D



Yolanda is the project manager of a high-profile project for her organization. This project has 124 stakeholders from across the organization and many of the stakeholders have high demands and expectations for the project. Yolanda will need several pieces of project information as she begins to communicate and manage the stakeholder expectations. Which of the following inputs of the manage stakeholder expectations process directly addresses the risks that could affect the project and which must be communicated to the project stakeholders?

  1. Change log
  2. Low-level risks watchlist
  3. Issue log
  4. Stakeholder register

Answer(s): A



Holly is the project manager of the NHQ project for her company. Her project sponsor, Tracy, has requested that Thomas, the department manager, from the Risk Management Department, will work with Holly to determine the effectiveness of the risk responses. Tracy and Thomas are concerned that some of the risks within Holly's project may not be addressed to depth they would like. In this scenario, who is responsible for ensuring that risk audits are performed at an appropriate frequency throughout the project?

  1. Thomas
  2. Tracy
  3. The project team
  4. Holly

Answer(s): D



You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. Which of the following inputs will be needed for the qualitative risk analysis process in your project? Each correct answer represents a complete solution. Choose all that apply.

  1. Organizational process assets
  2. Cost management plan
  3. Project scope statement
  4. Risk register

Answer(s): A,C,D



Page 32 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote