Adrian is the project manager of the NHP Project. In her project there are several work packages that deal with electrical wiring. Rather than to manage the risk internally she has decided to hire a vendor to complete all work packages that deal with the electrical wiring. By removing the risk internally to a licensed electrician Adrian feels more comfortable with project team being safe. What type of risk response has Adrian used in this example?

  1. Avoidance
  2. Mitigation
  3. Acceptance
  4. Transference

Answer(s): D



Linda is the project manager of the NAB Project. One of the risks her project team has identified is too dangerous for the project team to manage internally so she has hired a vendor to complete this portion of the project and to manage the identified risk. What risk response has Linda used in this instance?

  1. Transference
  2. Avoidance
  3. Contractual
  4. Mitigation

Answer(s): A



You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation if a selected risk strategy fails to be fully effective?

  1. Mitigation management plan
  2. Mitigation plan
  3. Fallback plan
  4. Risk response plan

Answer(s): C



You are the project manager of a large construction project. This project will last for 18 months and will cost $750,000 to complete. You are working with your project team, experts, and stakeholders to identify risks within the project before the project work begins. Management wants to know why you have scheduled so many risk identification meetings throughout the project rather than just initially during the project planning. What is the best reason for the duplicate risk identification sessions?

  1. The iterative meetings allow the project manager and the risk identification participants to identify newly discovered risk events throughout the project.
  2. The iterative meetings allow all stakeholders to participate in the risk identification processes throughout the project phases.
  3. The iterative meetings allow the project manager to discuss the risk events which have passed the project and which did not happen.
  4. The iterative meetings allow the project manager to communicate pending risks events during project execution.

Answer(s): A



You are the project manager for a construction project. The project includes a work that involves very high financial risks. You decide to insure processes so that any ill happening can be compensated. Which type of strategies have you used to deal with the risks involved with that particular work?

  1. Mitigate
  2. Avoid
  3. Accept
  4. Transfer

Answer(s): D