Yolanda is the project manager of a high-profile project for her organization. This project has 124 stakeholders from across the organization and many of the stakeholders have high demands and expectations for the project. Yolanda will need several pieces of project information as she begins to communicate and manage the stakeholder expectations. Which of the following inputs of the manage stakeholder expectations process directly addresses the risks that could affect the project and which must be communicated to the project stakeholders?

  1. Change log
  2. Low-level risks watchlist
  3. Issue log
  4. Stakeholder register

Answer(s): A



Holly is the project manager of the NHQ project for her company. Her project sponsor, Tracy, has requested that Thomas, the department manager, from the Risk Management Department, will work with Holly to determine the effectiveness of the risk responses. Tracy and Thomas are concerned that some of the risks within Holly's project may not be addressed to depth they would like. In this scenario, who is responsible for ensuring that risk audits are performed at an appropriate frequency throughout the project?

  1. Thomas
  2. Tracy
  3. The project team
  4. Holly

Answer(s): D



You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. Which of the following inputs will be needed for the qualitative risk analysis process in your project? Each correct answer represents a complete solution. Choose all that apply.

  1. Organizational process assets
  2. Cost management plan
  3. Project scope statement
  4. Risk register

Answer(s): A,C,D



You are the project manager of the HJU project for your company. This project will last for 18 months and has a project budget of $567,000. Robert, one of your stakeholders, has introduced a scope change request that will likely have an impact on the project costs and schedule. Robert assures you that he will pay for the extra time and costs associated with the risk event. You tell Robert that the change request may affect more areas of the project than just time and cost and that you are worried about the additional risks the change request will bring. What project management component is responsible for evaluating a change request and its impact on all of the project management knowledge areas?

  1. Project change control system
  2. Integrated change control
  3. Risk analysis
  4. Configuration management

Answer(s): B



Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk events that will affect the project schedule. Management has asked Amy to consider the affect of all the risks on the project schedule. What approach can Amy take to create a bias against risks that will affect the schedule of the project?

  1. She can create an overall project rating scheme to reflect the bias towards risks that affect the project schedule.
  2. She can filter all risks based on their affect on schedule versus other project objectives.
  3. She can have the project team pad their time estimates to alleviate delays in the project schedule.
  4. She can shift risk-laden activities that affect the project schedule from the critical path as much as possible.

Answer(s): A