Who is responsible for appointing the Project Manager?

  1. Corporate or Programme Management
  2. The Project Board
  3. The Executive
  4. Project Assurance

Answer(s): C



During which of the following activities is the Project Product Description created?

  1. Design and appoint the Project Management Team
  2. Prepare the outline business case
  3. Select the project approach and assemble the project brief
  4. Plan the initiation stage

Answer(s): B



Which of the following is NOT an objective of Initiating a Project?

  1. Understanding the scope of what is to be done and the products to be delivered
  2. Understanding the roles and responsibilities of the Project Management Team
  3. Understand how quality required will be achieved
  4. Understand how progress will be monitored and controlled

Answer(s): B



Which other management product is created when the Business case is updated during Initiating a Project?

  1. Post project review plan
  2. Risk Register
  3. Benefits Review plan
  4. Issue Register

Answer(s): C



Who is responsible for the initial creation of the Configuration Item records?

  1. Project Manager
  2. Team Manager
  3. Project Assurance
  4. Project Support

Answer(s): D