Which statement is an appropriate entry for the Lessons Log?

  1. This is the first time that the Ministry of Food Hygiene (MFH) has been involved in outsourcing.
  2. Based on feedback from other government departments, the Ministry of Trade and Industry has provided the names of two outsourcing companies that are unreliable and should not be included as potential service providers.
  3. The feasibility study estimated that the outsourcing project would take two years to complete.
  4. Only the Information Technology Division and Facilities Division will be outsourced.

Answer(s): B



Which statement is an appropriate entry for the outline Business Case heading within the Project Brief?

  1. 10-year service contract should be agreed with the selected service provider.
  2. External consultants were employed to conduct a feasibility study to identify the options, their likely costs and benefits.
  3. The project will run for two years and the benefits will be realized over 1a years.
  4. The project should be split into four management stages.

Answer(s): C



Which statement is an appropriate entry for the project approach heading within the Project Brief?

  1. The initial estimates from the feasibility study will be verified during the initiation stage.
  2. MFH must better manage suppliers' performance.
  3. The Information Technology Division and the Facilities Division will be outsourced to a single service provider.
  4. The Project Manager will be responsible for ensuring that the agreed project approach remains an appropriate choice.

Answer(s): C



Which statement is an appropriate entry for the Initiation Stage Plan?

  1. The Daily Log has been updated with the new risks which were identified while preparing the Initiation Stage Plan.
  2. The plan is based on the external outsourcing consultants being available at the start of the initiation stage.
  3. The initial project cost estimate of £2.5m, will have a tolerance of +£125k J•£75k.
  4. The project management team will consist of representatives from the IT and Facilities Divisions.

Answer(s): B



During stage 1 the level of performance expected from the service provider was changed. After this change was agreed which of these products will require updating?

  1. Project Brief because this is maintained throughout the project to reflect the customer's quality expectations.
  2. Project Product Description because this contains details of the expected performance of the project's products
  3. Quality Management Strategy because this is where all of the customer's quality expectations of the project's products should be documented

Answer(s): B