While preparing the Quality Management Strategy, the Project Manager noticed that the corporate quality management system does not specifically cover project management.
Which option provides an appropriate way for the Project Manager proceed?

  1. Record the development of a corporate quality management system for project management as a prerequisite of the Project Plan.
  2. Proceed with the project without a Quality Management Strategy and adopt the selected service provider's standards in stage 4.
  3. Seek relevant organizational standards, then facilitate a workshop to discuss the Quality Management Strategy with Project Assurance.

Answer(s): C



Which project controls should be established for the Outsourcing project?

  1. Highlight Reports to the Project Manager; Exception Reports to the Project Board when project tolerances are forecast to be exceeded
  2. Highlight Reports to the Project Board; Exception Reports to corporate management when stage tolerances are forecast to be exceeded
  3. Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or project tolerances are forecast to be exceeded

Answer(s): C



View Related Case Study

There is no project schedule in the Project Initiation Documentation. How can project progress be tracked without a schedule to track against?

  1. This is an error as a Gantt chart or some form of time line, where actuals will be recorded and tracked against the planned schedule of delivery, is mandatory.
  2. Progress can be recorded and tracked using the product checklist, with the planned and actual quality management activities captured in the Daily Log.
  3. With a clear end date of 30 November, and a small number of Work Packages, the Project Board should track project progress using individual Team Plans.

Answer(s): B



View Related Case Study

There is no Project Brief. How can there be a common understanding of the desired outcomes for the prepared calendar pack?

  1. The simple Project Initiation Documentation contains the Quality Management Strategy. This contains details of the acceptance criteria for this project.
  2. The Project Brief should have been produced and approved before the project progressed into the initiation stage.
  3. The simple Project Initiation Documentation contains the project definition.

Answer(s): C



View Related Case Study

There is no mention of any Stage Plans, yet there are two further stages proposed. How will this be resolved?

  1. It is appropriate for the Calendar project to be run as two further stages as there is a key decision to be made at the end of stage 2. Stage Plans will be produced.
  2. Whilst the activities are divided into two further stages, there is no reason why the Calendar project should use stages. The project will therefore be run as a single stage project and the activities will be added to the Initiation Stage Plan.
  3. There will be three Stage Plans, the two management stages plus an additional stage to plan and complete the activities of the Closing a Project process.

Answer(s): A