Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

  1. Issue Register
  2. Follow-on action recommendations
  3. Lessons Report
  4. Risk Register

Answer(s): C



View Related Case Study

Starting Up a project is triggered by which of the following?

  1. Legislation
  2. Corporate Strategy
  3. Risks
  4. Mandate

Answer(s): D



View Related Case Study

Who is responsible for appointing the Project Manager?

  1. Corporate or Programme Management
  2. The Project Board
  3. The Executive
  4. Project Assurance

Answer(s): C



View Related Case Study

During which of the following activities is the Project Product Description created?

  1. Design and appoint the Project Management Team
  2. Prepare the outline business case
  3. Select the project approach and assemble the project brief
  4. Plan the initiation stage

Answer(s): B