Which of the following is NOT an objective of Initiating a Project?

  1. Understanding the scope of what is to be done and the products to be delivered
  2. Understanding the roles and responsibilities of the Project Management Team
  3. Understand how quality required will be achieved
  4. Understand how progress will be monitored and controlled

Answer(s): B



View Related Case Study

Which other management product is created when the Business case is updated during Initiating a Project?

  1. Post project review plan
  2. Risk Register
  3. Benefits Review plan
  4. Issue Register

Answer(s): C



View Related Case Study

Who is responsible for the initial creation of the Configuration Item records?

  1. Project Manager
  2. Team Manager
  3. Project Assurance
  4. Project Support

Answer(s): D



View Related Case Study

Which statement is an appropriate entry for the Lessons Log?

  1. This is the first time that the Ministry of Food Hygiene (MFH) has been involved in outsourcing.
  2. Based on feedback from other government departments, the Ministry of Trade and Industry has provided the names of two outsourcing companies that are unreliable and should not be included as potential service providers.
  3. The feasibility study estimated that the outsourcing project would take two years to complete.
  4. Only the Information Technology Division and Facilities Division will be outsourced.

Answer(s): B