When updating the project plan as part of Managing a stage boundary, what else might be updated?

  1. Exception Plan
  2. Project Management team
  3. Business Case
  4. Project Initiation Documentation

Answer(s): A



Which of the following management products ARE updated as part of Managing a stage boundary?

1. Business Case
2. Benefits Review Plan
3. Configuration Item Records
4. Project Brief

  1. 1,2,3
  2. 1,3,4
  3. 1,2,4
  4. 2,3,4

Answer(s): A



Which of the following activities could trigger the production of an exception plan?

  1. Review Stage status
  2. Giving ad hoc direction
  3. Escalating a project issue
  4. Report stage end

Answer(s): B



Which of the following statements is FALSE regarding the Continued Business Justification?

  1. The justification for the project must remain the same throughout the project.
  2. The justification for the project should remain vabd.
  3. The justification for the project may change.
  4. If the project is no longer justified it should be stopped.

Answer(s): B