Free PRINCE2 PRACTITIONER Exam Braindumps (page: 37)

Page 36 of 71

Which of the following activities is NOT an action of preparing for planned closure?

  1. Update the project plan with actual
  2. Update the Project Management Team
  3. Request a product status account
  4. Confirm project has delivered what is defined in Project Product Description

Answer(s): B



Which principle is supported by the activity Evaluate the Project?

  1. Continued Business Justification
  2. Defined roles and responsibilities
  3. Learn from experience
  4. Manage by stages

Answer(s): C



HOTSPOT (Drag and Drop is not supported)
The Calendar project was delivered as originally planned, and Is now preparing for planned closure.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Hot Area:

  1. See Explanation section for answer.

Answer(s): A

Explanation:



The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?

  1. Scope, People & Resources, Benefit
  2. Scope, Risk, Product
  3. Risk, Benefit, Product
  4. Scope, Risk, Benefit

Answer(s): D






Post your Comments and Discuss PRINCE2 PRINCE2 PRACTITIONER exam with other Community members:

PRINCE2 PRACTITIONER Discussions & Posts