DRAG DROP
DIRECTING A PROJECT
Here are three actions that are carried out as part of the „directing a project‟ process. During which activity (A-E) should they be carried out?
Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
Select and Place:
Exhibit A:


Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



View Related Case Study

DRAG DROP
CONTROLLING A STAGE
Here are three activities that take place during the „controlling a stage‟ process. Which role (A-F) should carry out each activity? Choose only one role for each action. Each role can be used once, more than once, or not at all.
Select and Place:
Exhibit A:


Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



View Related Case Study

The project board has asked for highlight reports every six weeks during stage 3. As a result, the project manager has asked each team manager for checkpoint reports every six weeks, in order to collate these into the highlight report. The team manager for the “marketed courses” is new to team management.
Is this an appropriate action as part of the “controlling a stage” process, and why?

  1. Yes, because the project board will need to be updated with the progress of every team.
  2. Yes, because checkpoint reports are a time-driven control providing progress information.
  3. No, because the frequency of reporting should reflect the level of control required for the work package.
  4. No, because the project board should decide on the frequency and content of progress reporting.

Answer(s): B



View Related Case Study

MANAGING PRODUCT DELIVERY
The team manager for the production of the „marketing materials‟ has identified that they will not be ready within the timescale agreed in the work package. The team manager has sufficient tolerance to take corrective action. As a result, additional resources have been assigned to this work package.
Which theme is being applied?

  1. Risk
  2. Organization
  3. Progress
  4. Change

Answer(s): A



View Related Case Study

In order for ABC Company to achieve the expected sales of the health and safety training course, the senior user will need to ensure that all staff understand the objectives and target audience for the course. In addition, these sales will need to be added to each individual’s sales targets. These activities have been included in the benefits management approach.
Is this appropriate, and why?

  1. Yes, because how the benefits will be measured needs to be documented.
  2. Yes, because the actions required to achieve the outcomes need to be documented.
  3. No, because the expected sales increase should be recorded in the business case.
  4. No, because actions to deliver the outputs should be recorded in the stage plan.

Answer(s): A