Free PRINCE2 PRACTITIONER Exam Braindumps (page: 6)

Page 5 of 71
View Related Case Study

A quality review of the „marketing materials‟ has started. The team manager for the „marketing materials‟ has been unhappy with the team’s workload throughout the project and refuses to attend the review meeting to present the material. The team manager suggests that a new marketing team member make the presentation. However, the chair decides to represent the marketing team and makes a list of actions to resolve later. Is this an appropriate approach to the quality review, and why?

  1. Yes, because the role of presenter should not be performed by a junior member of the team.
  2. Yes, because the roles of chair, presenter and administrator may be combined.
  3. No, because the role of presenter should be performed by the team manager.
  4. No, because the chair should be independent from the product being reviewed.

Answer(s): D



View Related Case Study

DRAG DROP (Drag and Drop is not supported)
PLANS
Here are three events to managing plans for the project.
In which management product (A-E) should the result of each event be recorded?
Choose only one product for each event. Each product can be used once, more than once or not at all.
Select and Place:

  1. See Explanation section for answer.

Answer(s): A

Explanation:



View Related Case Study

The delivery of the pilot courses has been split into two separate products: „planned pilot courses‟ and „delivered pilot courses‟. „Planned pilot courses‟ will be produced during stage 3, and the „delivered pilot courses‟ will take place during stage 4. This will allow the project board to approve the plan for the pilot courses before the resources are committed to delivering the pilot courses. Why is this an appropriate application of the plans theme to control the project?

  1. Because a PRINCE2 project should focus on the quality of the products being delivered.
  2. Because the pilot courses have been broken down into two separate products.
  3. Because the project board should ensure that lessons from one stage are applied to the next stage.
  4. Because the delivery steps to create the pilot courses have been aligned to the management stages.

Answer(s): D



View Related Case Study

DRAG DROP (Drag and Drop is not supported)
The project is in stage 2. The project manager has heard that a competitor may launch a similar e-learning course much sooner than ABC Company. There is a threat that the earlier launch of a competitor’s course may reduce the profitability of ABC Company training courses.
Here are three responses to this risk. Which risk response type (A-F) are they?
Choose only one response type for each risk response. Each response type can be used once, more than once, or not at all.
Select and Place:

  1. See Explanation section for answer.

Answer(s): A

Explanation:






Post your Comments and Discuss PRINCE2 PRINCE2 PRACTITIONER exam with other Community members:

PRINCE2 PRACTITIONER Discussions & Posts