ABC Company carried out a similar project two years ago, in response to changes in health and safety legislation for the health service. The experiences from that project were used to refine the corporate risk management policy. For that reason, the project board decided to use the corporate risk management policy in the risk management approach for this project. Is this appropriate, and why?

  1. Yes, because experience from previous projects should be taken into account in the risk management approach.
  2. Yes, because the corporate risk management policy was updated, as a result of lessons from previous projects.
  3. No, because the risk management approach should be tailored to suit the project and its environment.
  4. No, because a separate risk management approach is not necessary when the company has a risk management policy.

Answer(s): A



View Related Case Study

An external consultant has signed a contract and agreed a work package to accredit the trainers. The Purchasing Manager will monitor the contract, which states the requirement to organize the accreditation with the Training Delivery Manager. The Training Delivery Manager has tried to contact the consultant but there has been no response. The project manager believes there is a risk that the consultant is prioritizing other clients‟ work. The Purchasing Manager has been assigned as the risk owner. Is this an appropriate approach to managing this risk, and why?

  1. Yes, because the Purchasing Manager is monitoring the contract and therefore best suited to controlling the risk.
  2. Yes, because the Purchasing Manager should have identified the risk when the work package was agreed.
  3. No, because the team manager should be the risk owner to risks concerning the delivery of a work package.
  4. No, because the risk was transferred to the Training Delivery Manager when the work package was authorized.

Answer(s): A



View Related Case Study

DRAG DROP (Drag and Drop is not supported)
CHANGE
A request has been received from a user to add the function to pay by credit card to the „amended course booking procedures‟ for the „e- learning course‟. The user has suggested that sales of the course will be reduced if this change is not implemented. Here are three actions relating to this request for change.

Which role (A-E) should carry out each action?
Choose only one role for each action. Each role can be used once, more than once, or not at all.
Select and Place:

  1. See Explanation section for answer.

Answer(s): A

Explanation:



View Related Case Study

The project’s change control approach states that PRINCE2‟s recommended issue and change control procedure will be used. The senior user has requested that a new set of marketing materials and marketing channels be introduced to support the launch of the training course. The senior user has suggested that this should be managed informally.
Where should the project manager record the issue, and why?

  1. In the daily log, because a change to a product at the default level can be handled informally.
  2. In the daily log, because the senior user has advised that this change should be informally.
  3. In the issue register, because this is a request for change requiring a change to a baseline.
  4. In the issue register, because issues should be recorded here first, before determining how to manage them.

Answer(s): D