At the end of stage 2, the specialist “e-learning course” supplier will be selected. As a result, it is decided that the quality management approach will not be created until the end of stage 2, to take into account this supplier’s standards and techniques. Is this appropriate, and why?

  1. Yes, because the quality management approach should take into account the supplier’s standards, tools and techniques.
  2. Yes, because the product description for each product will define the required quality approach within each stage.
  3. No, because the quality management approach should be created during the initiation stage and updated later.
  4. No, because the quality management approach should be limited to ABC Company’s quality standards.

Answer(s): A



View Related Case Study

The executive identified that there would be a benefit to the construction companies as their working time lost due to accidents would be reduced. This was included as a benefit to ABC Company in the business case for the Health and Safety Training Project. Is this appropriate, and why?

  1. Yes, because the benefits to the customer are an essential part of business justification for a project.
  2. Yes, because both tangible and intangible benefits should be included in the business case.
  3. No, because ABC Company will not achieve their benefits if construction companies do not book the courses.
  4. No, because it is the customer’s benefits that should be used to justify the project business case.

Answer(s): A



View Related Case Study

A construction company that is one of ABC Company’s key clients has agreed to provide a member of the staff to review and comment on the “e-learning course”.
Which stakeholder interest should the member of staff represent, and why?

  1. Supplier, because this stakeholder provides the expertise required by the project.
  2. Supplier, because this stakeholder is an external supplier.
  3. User, because this stakeholder may train its staff using the „e-learning course‟.
  4. User, because this stakeholder ensures that the project provides value for money.

Answer(s): D



View Related Case Study

Use the “Additional Information” in the Scenario Booklet to answer this question.
The Operations Director is the executive for the project and has proposed that a senior course developer be appointed as project manager. The course developer works in the Training Development Manager’s team and has a good understanding of the standard course development model. The course developer was a team manager on a previous project for which the Operations Director was the executive. Is this proposed appointment appropriate, and why?

  1. Yes, because the course developer is responsible for ensuring that trainers deliver courses to the required standard.
  2. Yes, because the course developer is likely to have the project management and specialist knowledge required.
  3. No, because the course developer’s team reports to the Business Development Director, not the Operations Director.
  4. No, because there is a conflict of interest as the Training Development Manager is responsible for gaining accreditation.

Answer(s): A



View Related Case Study

The “classroom-based training materials” will be used as the basis for developing the “e-learning course”. As a result, the executive wants to ensure that the “classroom-based training materials” are of the required standard. The executive has asked to meet the project manager every day during stage 2 to discuss progress and identify any concerns regarding quality.
Is this an appropriate approach to applying the organization theme, and why?

  1. Yes, because the executive should be available to provide ad hoc direction to the project manager.
  2. Yes, because the executive should be the key decision-maker on the project, supported by other project board members.
  3. No, because the senior user should be responsible for specifying the quality criteria for the training materials.
  4. No, because the project manager should be given authority to manage the project on a day-to-day basis.