When are tolerances for a Work Package agreed?

  1. When accepting a Work Package
  2. As work on each product within the Work Package begins
  3. Once ail products have been developed and approved
  4. When the Stage Plan is authorized by the Project Board

Answer(s): A



Which risk response type is appropriate to respond to an opportunity?

  1. Accept
  2. Fallback
  3. Exploit
  4. Transfer

Answer(s): C



Which is an objective of the Managing Product Delivery process?

  1. Sign-off completed Work Packages
  2. Ensure the Business Case is kept under review
  3. Report progress to the Project Board
  4. Ensure that work on products is authorized and agreed with the team

Answer(s): D



Which product is NOT created in the Managing a Stage Boundary process?

  1. Benefits Review Plan
  2. End Stage Report
  3. Lessons Report
  4. Exception Plan

Answer(s): A