Which is NOT an objective of the Controlling a Stage process?

  1. Implement actions to control the impact of risks that occur during the stage
  2. Review the Business Case at regular intervals to assess the impact of changes that occur during the stage
  3. Update the Business Case with any changes agreed with the Project Board
  4. Coordinate the delivery of products as agreed in the Stage Plan

Answer(s): C



If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

  1. Checkpoint Report
  2. Highlight Report
  3. Issue Report
  4. Product Status Account

Answer(s): C



Which is an objective of the quality review technique?

  1. To baseline a product
  2. To provide a common understanding of what products a project will create
  3. To define the quality methods required within a project
  4. To determine the quality responsibilities of a project team

Answer(s): A



Which is NOT a type of issue?

  1. A problem/concern
  2. A constraint
  3. An off-specification
  4. A request for change

Answer(s): B