Which describes a risk event?

  1. The area of uncertainty in terms of the threat or opportunity
  2. The derivation or sources of a potential risk to the project
  3. The achievement of a milestone on the Project Plan
  4. The sequence of events and actions that will be put in place if a risk occurs

Answer(s): A



What product defines the reporting requirements between the Project Manager and Team Manager?

  1. Project Brief
  2. Product Description
  3. Team Plan
  4. Work Package

Answer(s): D



Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?

  1. Defined roles and responsibilities
  2. Learn from experience
  3. Manage by exception
  4. Focus on products

Answer(s): B



What product should be used to confirm the version number of ail products in a particular stage?

  1. Issue Register
  2. Product Status Account
  3. Product Description
  4. Configuration Item Record

Answer(s): B