Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning?

  1. Scheduled orders
  2. Procurement orders
  3. Planned orders
  4. Stock orders

Answer(s): C



In which of the following is the Capacity planning Indicator set?

  1. Control Key
  2. Work Center
  3. Requirement
  4. Task

Answer(s): A



Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?

  1. Control key
  2. Confirmation key
  3. Scheduling key
  4. Customizing key

Answer(s): A



In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how?

  1. Automatic requirement grouping indictor
  2. MRP element indicator
  3. MRP groups
  4. Material group

Answer(s): B



What are the prerequisites for automatic requirements grouping on the top WBS element of a project?

  1. The "project stock" indicator is set in the project definition (either valuated or non- valuated)
  2. The "Valuated project stock" indicator must be set in the project definition.
  3. The MRP group of the components must permit requirements grouping.
  4. The project must be released.
  5. The top-level WBS element must be released.

Answer(s): B,C